EDGE 60 Pellet Fireplace
R
R
NOTICE:
•
Read and understand Sections 6 through 10 for detailed
information before installing the fireplace.
• Follow all clearances as specified.
• The choice of finishing material and decorative front
must be determined before installation can begin as it
will determine the placement of the fireplace.
• Outside air is required on all installations and the Out
-
side Air Kit must be ordered separately.
F. Recommended Order of Installation
1.
Identify the exhaust vent and outside air locations
and install necessary venting components including
wall thimble, fire stop or roof flashing for a verti
-
cal termination.
NOTE:
Outside Air Kit must be
ordered separately.
2.
Complete the framing.
.
Install the electrical junction box near the electrical
opening on the left side of the appliance. Maximum
distance of 7.5 feet (9mm) from appliance.
4.
Identify the location of the wall control and run the
wire (5 ft in length) to the left side of the appliance.
5.
Prepare the fireplace for the exhaust vent adapter.
Install adapter, seal with high temp silicone and
screws and install all cover plates.
6.
Preset the nailing flanges depending on the thick
-
ness of your finishing material.
7.
IT IS CRUCIAL FIREPLACE IS ROBUSTLY
SECURED. Slide the fireplace into place and
secure to the floor with the securing brackets and to
the wall. See
page 33
for detailed instructions.
8.
Attach the exhaust and outside air venting to the
appliance.
9.
Hook up power and the wall control.
10.
Slide the fireplace out on the rail system to validate
that it is secure and there is no deflection in the
outer can.
11.
A burn test must be performed
before finishing
material is installed
. (See Item “G”).
12.
Install the finishing material.
1. Install the decorative front.
• The fireplace must be secured in place as outlined in
Section 6.
• When servicing the fireplace, the fireplace slides
foward on the rail system.
• Tipping can occur if fireplace is not properly secured
to the floor.
G. Items to Verify During Test Burn
• Check for leaks in the exhaust venting system. Do you
see any smoke?
Remember on a first burn that odors and
vapors are released due to the curing of the
high temperature paint. The focus is on the
venting system.
• Check overall operation, are there any errors codes on
the Wall Control?
• Confirm that outside air is hooked up and properly
sealed. Is there cold air infiltration?
Crush Hazard!
• To avoid tipping over, this appli
-
ance must be securely fastened
to the floor.
WARNING