background image

Model EQ10 

Installation, Operation and Maintenance 

 

                   Page 8 

  

Rev. 11/30/2020

 

  

EQ

10-IOM-Q.

doc 

IMPORTANT

:

 

A

FTER WIRING HAS BEEN COMPLETED

,

 

TEST OPERATION OF 

P

OWER 

U

NIT 

&

 

O

VERHEAD 

L

IMIT 

SWITCH

.

 

W

HILE RAISING LIFT

,

 OPERATE 

O

VERHEAD 

S

HUTOFF 

B

AR

.

 

P

OWER 

U

NIT 

M

OTOR SHOULD STOP 

WHEN 

S

HUTOFF 

B

AR IS RAISED

C

OLUMN 

D

ECAL 

P

LACEMENT

 

43) Clean the surface of the columns before placing 

the decals. 

44) Apply the Safety Decals (Pg. 3) below the lock 

clevis on the power column and the Logo Decal 
48” above the base plate on the idler column. 

Fig 12

Fig. 12 – Safety & Logo Decal Placement

 

F

INAL 

A

DJUSTMENTS 

H

YDRAULICS

 

45) Lower the lift to the floor and raise the lift 

approximately one foot. 

46) Start with Idler side first. Slowly and carefully 

loosen the bleed plug on top side of the cylinder 
just enough to allow the entrapped air to escape. 
Repeat for power side. 

47) Raise lift 6 inches. Repeat previous step until no 

air comes out of the cylinders.  

48) Pressure test hydraulic system. Energize power 

unit, raise lift to full rise and continue to run 
motor for additional 10 seconds. (NOTE: 
pressure relief will make a high pitch squeal 

sound for these 10 seconds.) Check hydraulic 
system for leaks.  

49) Energize power unit again for 10 seconds. With 

a clean rag, wipe down both cylinder rods. (The 
cylinders are shipped with a small amount of 
clear anti-corosive lubricant that will be forced 
out through the wiper when the lift reaches full 
rise.) 

If lubricant is not wiped clean from the 

cylinder rod, the cylinder will apear to be 
leaking

S

YNCHRONIZING 

C

ABLES

 

50) Raise lift and ensure carriages lower into same 

lock position. 

51) Adjust synchronizing cables so the tension is 

equal in both cables and carriages are firmly 
sitting on locks. 

52) 

Cycle lift to ensure that latches operate 
simultaneously. 

L

OCK 

R

ELEASE 

C

ABLE

 

53) Raise lift to a lock position but don’t set into the 

lock.  Pull and release Power Column lock 
release handle while watching Idler Column lock. 

IMPORTANT: I

F IDLER SIDE LOCK PAWL DOES NOT 

FULLY DISENGAGE

,

 DAMAGE MAY RESULT TO IDLER 

SIDE CARRIAGE AND OR CABLE SYNCHRONIZING 
SYSTEM

Adjust cable tension by adjusting 

location of threaded cable lug on the mounting 
tabs. Cable clamps may need to be loosened.

 

54) After both locks fully disengage when the Power 

Column lock release handle is pulled down, 
tighten all clamps to secure lock release cable 
assembly.

 

55) Install both plastic lock covers ensuring lock 

cable assembly is routed thru formed guides in 
the covers.  Replace lock release knob.  Ensure 
lock release handle still disengages both locks 
with the lock covers in place.

 

F

INAL 

C

HECKOUT 

P

ROCEDURE

 

56) Demonstrate the operation of the lift to the 

owner/operator/employer using a typical vehicle 
and review correct and safe lifting procedures 
using the 

Lifting It Right

 booklet as a guide. 

57) Return all provided literature (including this 

manual) to the literature pack envelope and 
deliver the envelope to the 
owner/operator/employer. 

58) Complete the online warranty registration (refer 

to the included warranty statement). 

Summary of Contents for EQ10

Page 1: ...Post Surface Mounted Lift MODEL EQ10 QUALITY LIFTS LLC 2311 South Park Rd Louisville KY 40219 TOLL FREE 877 771 5438 FAX 502 583 5488 E mail sales qualitylifts com www qualitylifts com IMPORTANT READ...

Page 2: ...1 4 1899 mm 75 1 4 1975 mm with Adapter B Overall Height 143 7 8 3655 mm C Overall Width 131 3 4 3347 mm D Drive Thru Clearance 98 3 8 2499 mm E Floor to Overhead Switch 137 3482 mm F Short Arm Reach...

Page 3: ...ulted to address seismic loads and other local or state requirements Failure by purchaser to provide the recommended mounting surface could result in unsatisfactory lift performance property damage or...

Page 4: ...not provided with the lift shipment 10 wt anti foam anti rust hydraulic biodegradable oil Dexron III ATF INSTALLATION SAFETY REQUIREMENTS FOR INSTALLATION AND SERVICE Refer to ANSI ALI ALIS current ed...

Page 5: ...Fig 3 Column Shimming 10 Tighten power column anchors and recheck column for plumb Re shim if necessary Torque to 150 foot pounds to set anchors OVERHEAD LIMIT SWITCH 11 Raise and install Overhead Ass...

Page 6: ...e the idler hose long up the backside of the column and thru the plastic guide at the top of the extension Continue across the overhead through each of the guides as shown in Fig 8 and down the backsi...

Page 7: ...and apply anti seize to the three retaining rings and where the double screw makes contact with the base of the footpad 34 Ensure arm stop hardware is present and adequately tightened so that spring...

Page 8: ...ise If lubricant is not wiped clean from the cylinder rod the cylinder will apear to be leaking SYNCHRONIZING CABLES 50 Raise lift and ensure carriages lower into same lock position 51 Adjust synchron...

Page 9: ...1 2 3 4 5 6 L3 L2 L1 T3 T2 T1 FACTORY WIRED FOR 208 240V 6 4 2 5 3 1 RECONNECTIONS FOR 440 480V T3 T2 T1 T9 T6 T7 T4 T8 T5 FOR THREE PHASE M FOR SINGLE PHASE Wiring Diagram 1 L1 3 L2 5 L3 2 T1 4 T2 6...

Page 10: ...the lift inspectors are qualified and that they are adequately trained in the inspection of the lift The Owner Employer shall establish procedures to periodically maintain the lift in accordance with...

Page 11: ...vehicle by attempting to rock the vehicle Check adapters for secure contact with vehicle lift points If the vehicle seems unstable lower the lift and readjust the arms If the vehicle is stable raise t...

Page 12: ...d leaks Check adapters for damage or excessive wear Replace as required with genuine Challenger Lifts parts Check lock release activation When properly adjusted the idler column lock should rest firml...

Page 13: ...Model EQ10 Installation Operation and Maintenance Page 13 Rev 11 30 2020 EQ10 IOM Q doc Parts Breakdown...

Page 14: ...Model EQ10 Installation Operation and Maintenance Page 14 Rev 11 30 2020 EQ10 IOM Q doc...

Page 15: ...ex Nut 13 AB 9367 DLH 1 Power Unit 58 B2065 5 1 M10 x 55 Clevis Pin 13 14 AD 9367 1 1 Power Unit 3Phase 59 GJY12 3 7 Hairpin Cotter Pin JSJ5 03 02CH Shutoff Bar 60 X10 095 8 Nut M16 15 JSJ5 03 03 1 Sh...

Page 16: ...Q10 Installation Operation and Maintenance Page 16 Rev 11 30 2020 EQ10 IOM Q doc REVISIONS 11 30 2020 ADDED STEP TO CHECK THE ARM STOP BOLTS TO MAKE SURE THEY ARE TIGHT UPDATED LOCK RELEASE CABLE PART...