Chapter 4 Installation of 2U enclosures
13
4 Installation of 2U enclosures
Sequentially follow the installation checklist to install the 2U storage enclosure, which references the following
topics
Unpack and prepare the 2U enclosure
CAUTION Do not operate a storage enclosure outside the manufacturer's intended use.
l
Storage enclosures are suitable for connection to intra-building or non-exposed wiring or cabling only.
l
Storage enclosures are suitable for installation in locations where the National Electrical Code (NEC)
applies but are not suitable for Outside Plant (OSP) installations.
l
Customer facilities must provide for voltages with not more than ± 5% fluctuation. Customer facilities must
also provide suitable surge protection.
To unpack and prepare the 2U enclosure:
1. Prepare the site for the storage enclosure installation. This includes meeting all product specifications and
providing a clean, clear, static-protected environment prior to unpacking the enclosure.
2. Complete the following actions to complete inspection of the 2U enclosure:
a. Examine packaging for damage. This includes cuts, water damage, or shipment mishandling.
b. If there is damage, photograph and document it, but do not proceed. Retain original packaging for
returns.
c. Cut open the package lid to remove all items above the chassis, such as the rails and protective foam,
and set aside to gain access the chassis.
3. Locate two people to assist in moving the storage enclosure chassis in its plastic bag onto the mechanical
lift.
a. Position a person on each side of the storage enclosure, grasping the chassis sides, not the front or rear
panel.
IMPORTANT Almost all the weight of the storage enclosure is to the rear, so prepare to lift more
from the side of the chassis to the rear than the chassis side to the front.
b. Simultaneously lift the storage enclosure, using appropriate safe lifting technique while moving it to the