Chapter 5 Installation of 5U enclosures
33
Figure 24 Alignment between 5U chassis and rails, minus rear components for clarity
4. Complete the following actions to properly secure the 5U chassis on its rails:
a. Keep the 5U chassis stationary on the mechanical lift.
b. Conduct a visual inspection of both sides to verify the bottom of the storage enclosure chassis rests
squarely on the front of the bottom shelf of the outer rail and that the direction is straight in, not at an
angle.
5. Complete the following actions to insert the 5U chassis into the rack cabinet:
a. Facing the front of the enclosure, carefully exert even pressure on both sides of the storage enclosure
front, inserting the storage enclosure until the rack ear flanges are flush with the front rack posts.
b. Carefully lower the mechanical lift.
c. Thoroughly examine the rack rails for issues such as bowing, scraping, resistance, or indicators of
misalignment.
6. Complete the following actions to secure the 5U chassis:
a. Remove and set aside the operator's (ops) panel.
b. Thread a lock washer and then a washer onto each of 2 Panhead 10-32 screws.
c. Facing the front of the enclosure, insert a Panhead 10-32 screw with washers into the top and bottom
holes in the ops panel, then hand tighten firmly against front rack post with a Phillips screwdriver.