DO NOT TURN THE POWER ON TO YOUR 
SYSTEM UNTIL YOU HAVE READ THROUGH 
THE COMMISSIONING STAGES IN THE NEXT 
SECTION. POWERING UP IS PART OF THE 
COMMISSIONING SEQUENCES. DAMAGE 
MAY OCCUR IF YOU FAIL TO FOLLOW IT 
CAREFULLY.

————————————————————

————————————————————

Q

UATREAU TOUCH

INSTALLING THE QT553-B
————————————————————
STEP 1

A thermostatic mixing valve should be 
connected to the mains hot and cold 
supply and adjusted to feed a regualted 
40C supply. Included in the fitting kit is 
a 1/2”x 3/8” reducer. If your valve has a 

different outlet find a suitable reducer to 
adapt to 3/8”  

Using the 3/8” blue pipe enclosed cut a 
length to feed the hot mains water inlet 
on the left side of the QT553-B module.

As part of this installation you will also 
install a separate cold water supply 
Included in the fitting kit is a 1/2” x 3/8” 
reducer to adapt to the correct pipe size. 
The 3/8” isolators also included can be 
fitted to make it simpler to adjust flow for 
mains hot and cold if the thermostatic 
valve is out of reach. This will control the 
cold water mains feed that is fitted to 
the left rear low level fitting (labeled cold 
mains inlet). It will also feed the Pure inlet 
on the front top right hand side of the 
boiler control unit. (Alternatively an RO 
Water supply can be used for this - see 
notes for more details) to the left and the 
smaller 1/4” cold feed into the front right 
hand side of the QT553-B. 

Connect a John Guest 1/2” -3/8” reducer 
to this cold isolation valve and run a 
length of blue 3/8” PE pipe ready for 
connection to the cold mains water inlet 
alongside the hot water inlet.

To create the secondary cold inlet feed 
connect the 3/8” reducing T into the same 
3/8” pipe at the closest point to isolator 
and run a length of 1/4” pipe to the pure 
inlet on the right hand side of the QT553-B. 
Also connect the 1/4” isolation valve just 
before the inlet. This will be for control 
purposes.

STEP 2

With the QT553-B module on the right 
hand side of the cupboard connect the 
thermostatic hot and the mains cold 

INSTALL ATION

Summary of Contents for PureH2O Touch

Page 1: ...BOILING CHILLED SPARKLING HOT COLD Touch INSTALLATION GUIDE...

Page 2: ...PRE INSTALLATION CHECK LIST 3 TYPE AA AIR GAP 4 INSTALLATION 5 UNPACKING YOUR EQUIPMENT 5 INSTALLING THE QUATREAU TOUCH TAP 5 INSTALLING THE QT553 B boiler control module 7 INSTALLING THE CS20 8 IMPO...

Page 3: ...ed Mains Cold Water that will be used to feed a cold supply to the system 4 Drainage An approved Type AA fitting air gap must be used for the Venturi waste Either a trapped upstand or drain clamp can...

Page 4: ...le water device The interconnection pipe must run downhill as shown here into the Airgap connection Stage 2 provides a secondary non return valve in the grey adaptor whilst stage 2 provides an air gap...

Page 5: ...and electrical connection that will be in a plastic bag inside the packing A contents list will explain what should be included and what the parts are used for PRIOR TO INSTALLATION WE RECOMMEND THAT...

Page 6: ...nel faces forward towards the user position 180 degrees to the sink Now you can tighten the nuts until you have a firm fixing on both sides The comms cable hangs down and will connect into the QT553 B...

Page 7: ...ust flow for mains hot and cold if the thermostatic valve is out of reach This will control the cold water mains feed that is fitted to the left rear low level fitting labeled cold mains inlet It will...

Page 8: ...he boiler unit at the back Push gently until it clicks in Connect the power lead but do not turn on at this stage QUATREAU TOUCH INSTALLING THE CS20 Before installation of the chiller unit refer to th...

Page 9: ...ontrol unit 3 Install Thermostatic mixing valve and set to maximum temperature then reduce by 1 2 turn for 40C set point Connect the hot and cold feeds with isolators 4 Install Drain off saddle with t...

Reviews: