Instruction book
2012 2039 28
99
5
Operating instructions
5.1 Initial start-up
Safety
The operator must apply all relevant Safety precautions.
Procedure
For the position of the air outlet and the drain connections, see sections Introduction.
1. Consult the sections Electric cable size, Installation proposal and Dimension drawings
2. The following transport fixtures (1), painted red, must be removed:
Transport fixtures
3. Check that the electrical connections correspond to the local codes and that all wires are clamped tight to
their terminals.
The installation must be earthed and protected against short circuits by fuses of the inert type in all phases.
An isolating switch must be installed near the compressor.
4. Check transformer for correct connection (CPT1). Check the settings of drive motor overload relay (OL1).
Summary of Contents for QGV 40
Page 2: ......
Page 16: ...Instruction book 2012 2039 28 16 Main components Main components...
Page 128: ...Instruction book 2012 2039 28 128 Appendix 1 Product Analysis Report...
Page 131: ......