22
Raita
PA bio - biokem
MANUAL - INSTALLATION
Content of the delivery, connercting etc
Piping, ventilation
Electricity
Installation posibilities
Installation in the ground
Other things ground installation
Anhcoring the tanks
Other thing ground installation
Electricity
A one-phase line (1) (ground cable) (cross-sectional area 1.5 / 2.5 / 4 mm2 according to the treatment plant model)
is led and connected to the control cabinet. Fuse power is usually 10 A / 16 A / 20 A / 25 A The cable is connected in
the control cabinet when other installations are ready.
The control cabinet is placed in the vanity at the mini-cleaner. It can also be placed for longer distances, for example
to the house wall, or inside the house.
(1)
(2)
2-3
2-3
K