5.5
Fall Stop Assembly
5.5.1 General
The slack fall stop is a safety stop, not a functional stop. The fall stop must be located at least six
(6.0) inches [150mm] from end of last chain link.
Figure 8. Cross Section of Slack Fall Stop
5.5.2 Fall Stop Installation
1. Position two fall stop halves (item 1,
Figure 8
) on chain link at least six (6.0”) inches [150mm] from
end of load chain.
2. Insert screw (item 2) through fall stop halves and chain link.
3. Tighten nut (item 3) per torque setting in section 6.4.