29
PLANNING
1. Select Operation Plans and the Add button in the upper, right corner. The Create
Operation Plan window will open.
2. Enter a Name for the plan.
3. Enter a Swath Width that matches the implement width.
NOTE:
If using tram lines, enter the width of the planter.
4. If desired, select Tramlines Setup. The Tramlines Setup window will open.
FIGURE 13. Tramlines Setup
NOTE:
Tramlines are spaces between rows that are not planted so future
operations in that field (such as spraying) will not drive over rows of
crops.
5. In the S1: Enter the number of swaths before the first tramline or extra wheel
width wills start. Typically, this will be the number of planter swaths it takes to
apply half of the sprayer width.
NOTE:
Adjust any of the cells on the Tramlines Setup page automatically
adjusts the Sprayer Width cell on the right side of the window.
6. In the W1: Enter the value for the extra width of one of the side tires. This is
typically the wheel width plus a few inches.
7. In the W2: Enter the value for the extra width of one of the side tires. This is
typically the wheel width plus a few inches.
8. In the S2: Swath Between Tramlines cell, desired number of swaths between the
tramlines. Generally this will be the number of planter swaths it takes to cover one
pass for the sprayer.
9. Press Accept
.
10. Press Create. The Region Settings window will open.