P/N 016-0171-675 Rev. A
29
INSTALLATION
CONNECT TANK TO FILL STATION
1. Connect tank one to fill side one of the fill station with 1” hose. Secure with the supplied hose clamps.
2. Connect tank two to fill side two of the fill station with 1” hose. Secure with the supplied hose clamps.
CONNECT FILL STATION TO PUMP
1. Connect the chemical port on top of the fill station to the pump with 1” hose. Secure with the supplied hose
clamps.
CONNECT RINSE
1. Connect the 3/4” hose to the rinse port of the rinse 3-way valve located under the rinse tank. Secure with the
supplied hose clamps.
2. Route the hose to the rear of the machine and connect the rinse port of the pump plumbing. Secure with the
supplied hose clamps and zip ties.
CONNECT PUMP RECIRCULATION OUTLET TO TANK
1. Connect the pump recirculation outputs to tank one and two recirculation ports with 1/2” hose. Secure with the
supplied hose clamps.
CONNECT PUMP TO INJECTION POINT
1. Connect the pump output to the injection point on the mixer with 1/2” hose. Secure with the supplied hose
clamps.
CONNECT OVERFLOW
1. Connect a 1” hose to the overflow ports on the top of the tank. Secure with the supplied hose clamps.
2. Route the hose down the side of the cage. Secure the hose to the cage using the supplied zip ties.
TWO TANKS WITH TWO PUMPS PLUMBING INSTALLATION
NOTE:
Refer to Figure 5 on page 50 for a plumbing schematic for two tanks with two pumps.
Summary of Contents for ICD Sidekick Pro
Page 48: ...CHAPTER 5 44 ICD Sidekick Pro Injection for Case Trident Installation Manual ...
Page 57: ...P N 016 0171 675 Rev A 53 SYSTEM DIAGRAMS ...
Page 58: ...CHAPTER 6 54 ICD Sidekick Pro Injection for Case Trident Installation Manual ...
Page 60: ...INDEX 56 ICD Sidekick Pro Injection for Case Trident Installation Manual ...