30
INITIAL SYSTEM SET-UP
1)
With
NO
product in bin.
2)
Place boom ON/OFF switches to OFF.
3)
Place RATE 1/RATE 2/MAN switch to MAN.
4)
Place POWER ON/OFF switch to ON.
5)
Verify correct Boom Widths, SPEED CAL, METER CAL, VALVE CAL, and RATE CALS have
been entered in the Console.
6)
Enter into SELF TEST the normal operating speed.
7)
Place boom ON/OFF switches to ON.
8)
Verify that each boom operates by operating boom ON/OFF switches.
9)
Hold the INC/DEC switch in INC position for approximately 12 seconds. Note maximum
rate displayed in RATE display.
10)
Hold the INC/DEC switch in DEC position for approximately 12 seconds. Note minimum
rate displayed in RATE display.
11)
The target application rate must be between the maximum and minimum rate displayed.
INITIAL SYSTEM FIELD TEST
l)
Drive down field or road at target speed with boom ON/OFF switches OFF, to verify
SPEED readout on Console.
2)
Turn on appropriate boom switches, and place the RATE 1/RATE 2/MAN switch to RATE
1. Increase or decrease speed by one MPH [2 km/h]. The system should automatically
correct to the target application rate.
3)
If for any reason, the system is unable to correct to the desired RATE, check for
improper vehicle speed or a defect in the system.
4)
If the system does not appear to be correcting properly, first review INITIAL
SYSTEM SET-UP, then refer to SERVICE MANUAL and TROUBLESHOOTING GUIDE.
5)
At the end of each row, switch the boom ON/OFF switches to OFF to shut off
application. This also shuts off the area totalizer.
6)
Verify area covered and volume used.
Summary of Contents for SCS 660
Page 1: ...SCS 660 FOR GRANULAR APPLICATIONS INSTALLATION AND SERVICE MANUAL...
Page 2: ......
Page 10: ...8 BATTERY CONNECTIONS FIGURE 10...
Page 48: ......
Page 49: ......
Page 50: ......
Page 52: ...Manual Rev E SCS 660 9 97 Order 50 9 11 97 016 0159 572...