17
INSTALLATION INSTRUCTIONS
COMMISSIONING
7. COMMISSIONING
ON COMPLETION, THE INSTALLATION MUST BE
CHECKED FOR SAFETY. THE TESTS MUST INCLUDE:
• POLARITY CHECK
• EARTH BOND CONTINUITY
• INSULATION RESISTANCE CHECK
IMPORTANT
IF THERE IS NO MAINS SUPPLY OR THE ABOVE
TESTS CANNOT BE CARRIED OUT, ENSURE THAT A
WARNING LABEL IS ATTACHED TO THE APPLIANCE
STATING THAT IT SHOULD NOT BE USED UNTIL
ELECTRICALLY TESTED BY A SUITABLY QUALIFIED
ELECTRICIAN AND INFORM THE CUSTOMER.
Finally:
• Complete the Appliance Commissioning Checklist on
page 3
of this
User and Installation guide.