Pyrotech Zero Clearance Timber Frame Installation
Floor
0 mm
Sides
50 mm
Top
100 mm
Flue Outer
50 mm
CLEARANCES FROM
COMBUSTIBLES
NOTE:
Note: If fire is to be installed off the floor with 4
sided trim, use same A, B, C and D dimensions as shown
with frame work included below fire to required height.
Plasterboard to run beyond stud as shown,
and to go behind fixing flange on unit.
Min 50mm
clearance
NOTE
PYROTECH ZERO CLEARANCE MODEL
IMPORTANT
Install unit and
fluing before
plasterboard.
A
A
B
B
C
C
D
(Recommended only)
From hearth
Approx 20mm for
hearth if required.
D
(Recommended only)
HEATER
TRIM
Plaster to run
beyond stud
and behind trim
9