9. CENTRAL HEATING UNIT 
 
The instructions for installing a stove with a central heating coil are the same 
as for the basic unit. The central heating system should be installed as a two-
line system. (see drawing). 
 

SYSTEM WITHOUT CIRCULATION PUMP RUN 

To obtain the necessary circulation of hot water, the hot water pipes should rise 
approx. 5 cm (2”) per 100 cm (39”) rum. 
 

SYSTEM WITH CIRCULATION PUMP

 

The circulation pump is installed on the return pipe to the stove. (see drawing). 
 

EXPANSION TANK

 

All systems should be installed with an expansion tank close to the stove on the 
hot water side of the system. The tank must be the highest part of the heating 
system. (see drawing). 
 

HOT WATER SAFETY VALVE

 

The central heating system should be fitted with a hot water over heating safety 
valve, so that any over heating of the system will shut off fuel oil supply. (see 
drawing). 
 
In the event of the hot water over heating safety valve being tripped, the system 
must first cool down, whereby the safety valve can be reset by pressing the reset 
button on the cut off unit on the fuel line. 
 
THE CENTRAL HEATING SYSTEM SHOULD BE PROTECTED AGAINST FROST DAMAGE BY THE USE OF 
A SUITABLE ANTI-FREEZE. 
 

A frozen system must never be ignited.

 

 

 
10. THE REGULATOR 
 
The regulator is the heart of the oil stove. It controls the flow of fuel oil to 
the burner. There are 3 tapped connections in the bottom of the regulator for 8 
mm copper pipe. (See sketch). 
 
Overflow should be connected to a waste oil tank which should be placed at a 
lower level than the regulator. Under conditions of bad weather and heavy seas 

Summary of Contents for 2000K

Page 1: ...Tel 49 0 40 8890100 www toplicht de Schiffsausr ster...

Page 2: ...s steel boiler for connecting to central heating unit W Fitted with bulkhead fittings and built in regulator C Air intake duct 1 Kcal 3 97 BTU 1 BTU 0 25 Kcal The heating capacity of an oil stove is c...

Page 3: ......

Page 4: ...ecause of the negative air pressure created inside Oil stoves mounted in the engine room should always have their own outside air supply because the motor takes air from the stove In Denmark the Minis...

Page 5: ...ion We recommend that there should be insulation behind and over the stove and that the relevant country Ministry of ship surveyor rules for insulating and covering of bulkheads as shown in the drawin...

Page 6: ...2000 mm 78 and min 200 mm 8 above the oil stoves regulator The tank is supplied with a brass compression ring and nut so the 8 mm diameter copper fuel pipe can be easily fitted A heat sensitive safety...

Page 7: ...E The central heating system should be fitted with a hot water over heating safety valve so that any over heating of the system will shut off fuel oil supply see drawing In the event of the hot water...

Page 8: ...min Model 2000K and 2000KV 3 5 9 cc min All regulators are set by the factory for diesel oil with an oil viscosity of 4 0 at a temperature of 20 degrees centigrade Diesel oil evaporates at approx 77...

Page 9: ...1 Open the top of the stove and drop a lit match down into the bottom of the burner pot If methylated spirit is used to light the stove approx 5 cc should be poured directly into the burner pot and a...

Page 10: ...pot either with a vacuum cleaner or the special Refleks cleaning shovel The burner pot should be removed from the stove every 2 years for a more thorough cleaning CLEANING THE FLUE PIPE Remove the cow...

Page 11: ...PARTS The stove type should be quoted on ordering any spare parts This can be obtained from the name plate mounted over the cleaning pin In the event of this being unreadable the stove diameter and t...

Page 12: ...t to cool first 2 Never light a heater with a surplus of oil in the burner 3 Never leave the heater top lid open it should only be opened to light the stove and then closed immediately 4 Always ensure...

Reviews: