Manual - TC.P Quadro
Commissioning
2016-08-05
46/330
V04.52
3
3.2.3.
Installation instructions
These installation instructions apply to standard TopCon power supplies
with a complete case and air cooling (if not otherwise stated).
General information
Possible damage!
Due to soiling and foreign bodies at the installation location.
Due to a build-up of heat.
Avoidance:
The installation location must be free of conductive and ag-
gressive substances as well as moisture.
No foreign bodies such as drilling swarf or screws are to be
allowed to fall into the system.
It imperative you observe the minimum distances during in-
stallation.
The ventilation openings on the front panel and rear wall of
the devices must not be covered or sealed under any circum-
stances.
Case installation/delivery with case
TopCon power supplies are installed in standard cases or switch cabi-
nets either separately or in multi-unit systems.
In the standard design TopCon power supplies are intended to be in-
stalled in standard 19” cases and switch cabinets with an external air
flow. In this case they are to be placed on rails or shelves and fastened
at the points provided on the front panel.
Number of screws:
For 6 U devices typically: 4 x screws M6.
For 9 U devices typically: 6 x screws M6.
On installation in cases or switch cabinets, the following points are to be
noted:
Use robust rails or shelves (from the case/cabinet manufacturer):
the cases for TopCon power supplies must be in contact over the
full installation depth.
At the rear a cross-member is to be installed for additional fas-
tening of the power supplies.
Suitable transport aids must be used for the installation and re-
moval of the power supplies. E. g. fit the carrying handles sup-
plied in the side walls of the power supplies.
The power supplies are to be lifted at these handles.
CAUTION