Manual - TC.P Quadro
Commissioning
2016-08-05
68/330
V04.52
3
3.2.5.
Commissioning
– electrical power supply
Possible mortal danger due to electric shock!
Avoidance:
Installation and commissioning are only allowed to be under-
taken by appropriately skilled personnel.
During commissioning, proceed as per the following list step-
by-step.
Prior to switching on for the first time
Prior to switching on for the first time, the following points are to be
checked:
Does the information on the type plate match the mains connec-
tion and load?
Mains connection correctly wired?
Adequate cable cross-section used?
For further information see chapter 3.2.4.3, page 54.
Loads connected with correct polarity?
For further information see chapter 3.2.4.5, page 60.
Control signals connected correctly?
For information on X101/X102 see chapter 3.2.4.6, page 60.
For information on X105 see chapter 3.2.4.7, page 64.
Interlock/emergency stop circuit wired?
For further information see chapter 3.2.4.8, page 65.
3.2.6.
Switching on the device
Condition:
All external control signals for controlling device on/off must
be inactive.
All circuit breakers must be switched on.
On switching on the circuit breakers all LEDs illuminate for
approx. 1 s and the DSP controller starts a
device self-test.
Device self-test
The duration of the device self-test is approx. 5 seconds.
In multi-unit operation the system is also configured and the communi-
cation between the power supplies connected checked for correct func-
tion.
CAUTION