DIRECT FLUE ZERO CLEARANCE TOP EXIT VERTICAL FLUE KIT
INSTALLATION INSTRUCTIONS -946-632
This flue kit has been manufactured for use with FG39 and to be installed in
accordance with AS/NZS 5601. To ensure safety and correct unit operation
this flue kit must be installed as outlined in these instructions. Heater and
flue clearances from combustible materials must be in accordance with these
instructions and AS/NZS 5601.
1. Locate the heater in its proposed position and mark the point for penetra-
tion directly above the centre of the heater flue outlet. Check the heater
location allows the outer flue to clear all structural timber and combustible
surfaces as per the manual.
2. If the enclosure consists of a ceiling – cut a 255mm square hole (minimum)
for the flue to penetrate, cut hole through roofing material and prepare
flashing for termination.
3. Starting at the heater, install first length of inner pipe, crimped end down,
using Mill-Pac sealant and self-tapping screws (or rivets). Note – first length
of inner pipe has a swage only.
4. Continue assembling flue pipes inner and outer, ensuring each inner join
is sealed using Mill-Pac sealant and self-tapping screws (or rivets). Outer
flue pipe is to be installed with crimped end up then sealed and fixed
together also.
5. If required, fix outer flue in the ceiling space using non-combustible brac-
ing to stop movement. On penetration of roof, fit an appropriate flashing
or weather seal to suit the roofing material, ensure all joints outside are
sealed with appropriate sealer.
6. Fit gas cowl or flomet cap (946-651) ensuring inner and outer flue pipes
are sealed.
7. Start heater and run for at least 15 minutes to check flue seal. If operational
issues are noted, check flue again to ensure proper seal of inner pipe.
SUPPLIED
Mill-Pac SEALANT MUST BE USED OR WARRANTY WILL BE
VOID – IF REQUIRED, MORE SEALANT CAN BE PURCHASED USING
PART NUMBER 948-128
Gas cowl part number 46DVA-VCH or Flomet cap part number (946-651).
SCREWS SUPPLIED FOR INNER FLUE CONNECTION
45º bends (if required) part number 946-649 –
Note: if bends are used at
the start of flue run, a deeper crimp may be required at the unit for inner pipe
fitment. Can be crimped on site and sealed with Mill-Pac sealant and self-
tapping screws (or rivets).
Note – It is the installers responsibility to ensure the installation complies with
AS/NZS 5601 and all local and building codes.
NOTE:
USE A MINIMUM OF 3 SCREWS
EQUIDISTANT TO SECURE EVERY
INNER FLUE PIPE JOINT AS WELL
AS MILL-PAC SEALANT
Mill-Pac SEALANT
INNER FLUE
Screws
1st Length Inner Flue
has Deep Crimp
and is marked (crimp down)
Outer Heat Shield
174mm dia x 900mm x 4
Inner
100mm dia x 900mm x 4
Part Number: 946-651
flue
3 black lengths