HZ42ST Regency Horizon
TM
Gas Fireplace
12
INST
ALLA
TION
INSTALLATION
Note: When constructing the framed opening, please ensure there
is access to install the gas lines when the unit is installed.
2)
The unit does not have to be completely enclosed in a chase. You
must maintain clearances from the vent to combustible materials: See
"Clearances" section. Combustible materials can be laid against the
side and back standoffs and the stove base.
3)
Non-combustible material (ie. tile, slate, etc) may be brought up to and
overlap the unit (top and bottom) ensuring that the maximum thick-
ness does not go beyond the 1-1/2" as shown in the diagram below.
The faceplate will not be able to be mounted if the fi nished material
is beyond 1-1/2".
FRAMING & FINISHING
1)
Frame in the enclosure for the unit with framing material.
IMPORTANT: Vertical studs and the header must be metal.
Note:
Depending on the material used for fi nishing, the nailing strips must be
set accordingly so that the fi nished material is always at the 1-1/2" edge
of the fl ange.
4)
If material such as brick, stone, etc. extends past the faceplate depth,
when fi nishing around the faceplate, the minimum opening dimen-
sions noted below must be adhered to ensuring for the removal of the
faceplate and for the safe operation of this appliance.
Finished
Material
Nailing Strip
Position
1/2"
1"
1"
1/2"
1-1/2"
0" (fl ush)
Unit
Nailing Strip
1” Forward
Unit
Nailing Strip
½” Forward
Unit
Nailing Strip
Flush w/unit
Factory Set