Regency PG121/PG131 Zero Clearance Room Sealed Gas Fireplace
10
FRAMING AND FINISHING
CAUTION: The unit does not have to be completely enclosed in a
chase. The clearance on top of the unit is 0" to the standoffs so
combustible building materials can be laid directly on top of the
standoffs. You must maintain clearance from the flue to combustible
materials for both rigid and flex.
PG121-1 - See Thru
PG131-1 - Pier
Framing Dimensions
PG121 (See Thru) PG131 (Pier)
PG121LC / PG121RC
(Corner Unit)
A
25"(635mm)
25"(635mm)
26-13/13"(660mm)
minus two times minus two times
minus two times
the finishing
the finishing
the finishing
material thickness* material thickness* material thickness*
B
42-1/2"(1080mm) 42-1/2"(1080mm) 42-1/2"(1080mm)
C
46-3/4"(1187mm) 45" (1143mm)
45"(1143mm)
minus one time
minus one time
the finishing
the finishing
material thickness* material thickness*
Note: These units are
non-load bearing.
PG121LC-1 - Corner Unit
* Finish material thickness includes: drywall, ceramic tile, slate, etc.
1) For ease of installation, frame your fireplace after it is positioned and
the flue system is installed. Remember to install the top standoffs.
Use 2x4's and frame to local building codes.
2) When locating your appliance on an exterior wall or in a chase, apply
a vapour barrier and drywall, as per local building codes.
DO NOT
INSULATE THE FIREPLACE ITSELF.
CAUTION: Verify your fireplace dimensions, framing methods and
finished wall facing details before framing. Determine the total thick
-
ness of facing material - drywall plus ceramic tiles, slate, etc. Allow
the finish surface to be flush with the front or side of the unit. Total
facing thickness can vary from 1/2" (13mm) to 1-1/4" (32mm) thick.
PG121RC-1 - Corner Unit
INSTALLATION