15
• Install the strut between the two triangular supports
(Fig. 18). Following Fig. 18, insert special M8 nuts into
the triangle support rail. Then lay the strut onto the
rails and fasten it with M8x12 bolts with washers (Fig.
18).
• Continue assembling the remaining triangular supp-
orts with a pitch as shown in Fig. 2. Adjust this distan-
ce so that the pitch of the triangular supports is similar
to that of roof anchors in Fig. 2 and the last support
shall be located about 350 mm from the ends of both
rails.
After
fi
tting the strut and other supports, kip the
entire structure into the position intended for
collector installation. (The strut is upright, T rail
of each triangular support lies on the ground.)
spanner No.13
3
strut
2
c
Fig. 19: Installation of further supports
Fig. 17: Assembly using special bolts.
Fig. 16: Assembly using special bolts.
Special nut
for rails
rail
M8x12 bolt with
allen head
L strut
Fig. 18: Strut installation
Summary of Contents for KPG1-ALC
Page 1: ...1 1 Solar System with KPG1 ALC Collectors EN v 1 4 Installation and Operation Manual...
Page 26: ...26 84 70 6 1 1 2151 2010 70 1212 1170 21 21 22 15 CONNECTION DIMENSIONS...
Page 28: ...28...
Page 30: ...30...
Page 31: ...31...