5 Before installation
5.1
Installation regulations
Warning
The installer must be registered with Gas Safe and have the
correct ACS qualifications.
Important
Practical guidelines - see the latest version.
5.2
Choice of the location
5.2.1
Data plate
The data plate on the boiler features the boiler serial number and
important boiler specifications, for example the model and unit category.
The factory setting codes CN 1 and CN 2 are also stated on the data
plate.
5.2.2
Location of the boiler
A 500 mm (if the air supply filter is used, there must be a clearance
of at least 650 mm)
The standard inspection and maintenance operations to the boiler are
carried out from the front. This is also where the inspection ports of the
heat exchanger are located. The hydraulic connections and the flue gas
outlet are located at the front of the boiler. The control panel housing is
also on the front of the boiler.
Use the guidelines and the required installation space as a basis for
determining the correct place to install the boiler.
When determining the correct installation space, take account of the
permitted position of the flue gas discharge and/or air supply outlet.
Ensure that there is sufficient space around the boiler for good access
and ease of maintenance.
Fig.15
Position of data plate
AD-0001162-01
Fig.16
Clearance required
AD-0001163-01
80
0
10
0
10
0
65
7
50
11
00
1
6
6
2
A
5 Before installation
24
7665063 - v.05 - 18102018