8
4 Operation
4 Operation
4.1 When the working day begins
1. Put the Tank Grid in place
(see figure 1 Tank Grid).
2. Put the basket wheel in place (see Figure 2
Basket wheel).
Make sure it has fallen into place on the 4
support wheels.
Figure 1: Tank Grid
Figure 2: Basket wheel
3. Close the drain valve on the right side of the
machine (see Figure 3 Drain Valve).
4. Turn on the main power switch.
Figure 3: Drain Valve