11
Commissioning, Operation and Maintenance
11.1
Start-Up
11.1.1
General Information
The following commission notes refer to the GTE planetary gearboxes as part
of a drive-system with motor, drive and control unit.
11.1.2
Preparation
1. Keep the documentation of all products you are using ready.
2. Log all measures taken in the commissioning log.
3. Check the products for damage.
4. Check all mechanical and electrical connections.
5. Activate the safety and monitoring equipment of the system.
Damage to property due to errors in the con‐
trols of motors and moving elements! Unclear
operating states and product data!
NOTICE
●
Do not carry out commissioning if connections, operating states or prod‐
uct data are unclear or faulty!
●
Do not carry out commissioning if the safety and monitoring equipment
of the system is damaged or not in operation.
●
Damaged products must not be put into operation.
●
Contact Bosch Rexroth for missing information or support during com‐
missioning!
11.1.3
Bulk Head Connector
When all requirements are met, proceed as follows:
1. Commission the motors, controllers and power supplies according to the
corresponding descriptions. Note the respective product documentation.
2. Before releasing the setpoint, check whether the set relationship of the
maximum motor speed and the preset setpoint corresponds to the spec‐
ifications for the machine.
3. At a low turning speed, check whether the rotation direction of the gear‐
box and the polarity setpoint correspond to the specifications for the ma‐
chine.
4. At a low turning speed, check whether the positioning commands of the
control systems are executed correctly.
5. Log all measures taken in the commissioning report.
When all steps have been executed correctly, commissioning of the gearbox
is complete.
Commissioning of motors and controllers may require additional steps.
The inspection of the functioning and performance of the systems is not part
of the commissioning of the gearbox; instead, it is carried out within the
framework of the commissioning of the machine as a whole. Observe the in‐
structions and regulations given by the machine manufacturer.
DOK-GEAR**-GTE********-PR08-EN-P
Rexroth GTE Planetary Gearboxes
Bosch Rexroth AG
71/83
Commissioning, Operation and Maintenance
Summary of Contents for GTE Series
Page 6: ...Bosch Rexroth AG DOK GEAR GTE PR08 EN P Rexroth GTE Planetary Gearboxes IV 83 ...
Page 26: ...Bosch Rexroth AG DOK GEAR GTE PR08 EN P Rexroth GTE Planetary Gearboxes 24 83 ...
Page 32: ...Bosch Rexroth AG DOK GEAR GTE PR08 EN P Rexroth GTE Planetary Gearboxes 30 83 ...
Page 58: ...Bosch Rexroth AG DOK GEAR GTE PR08 EN P Rexroth GTE Planetary Gearboxes 56 83 ...
Page 68: ...Bosch Rexroth AG DOK GEAR GTE PR08 EN P Rexroth GTE Planetary Gearboxes 66 83 ...
Page 78: ...Bosch Rexroth AG DOK GEAR GTE PR08 EN P Rexroth GTE Planetary Gearboxes 76 83 ...
Page 82: ...Bosch Rexroth AG DOK GEAR GTE PR08 EN P Rexroth GTE Planetary Gearboxes 80 83 ...
Page 85: ...Notes DOK GEAR GTE PR08 EN P Rexroth GTE Planetary Gearboxes Bosch Rexroth AG 83 83 ...