FIGURE 23
DIRECT VENT VERTICAL TERMINATION DETAIL
ST-A1194-18-XO
DIRECT VENT (cont.)
GENERAL VENTING REQUIREMENTS AND
GUIDELINES
Figure 23
below shows the necessary detail for the roof penetration on a standard direct-vent vertical termination.
*3” (8cm) minimum only if no snow accumulation is anticipated.
Ve
nting
Terminations more than 24”
above roof penetration re-
quire additional support.
*
12” (31cm) U.S.
CANADA: TERMINATIONS
MUST CONFORM TO
CSA B149.1-10, SECT. 8.14
48” MAX.
(122 cm)
45” MAX.
(114 cm)
36” MAX.
(91 cm)
3” MIN.
(8 cm)
NOTE:
IF 3
Ø VENTING IS
USED, BOTH PIPES (INTAKE
AND EXHAUST) MUST BE
REDUCED TO 2
Ø BEFORE
PENETRATING ROOF.