background image

RICE HYDRO EQUIPMENT MFG., INC. 

MANUFACTURER’S OPERATING INSTRUCTIONS-ELECTRIC POWERED 

TEST PUMP MODEL TRE-8 

FOR WARRANTY INFORMATION CALL (800)245-4777. 

COMPONENTS: 

1.

 

208-230/460

 

volt, 3 phase, 

10 H.P., TEFC

 

electric motor equipped with 

heavy duty switch box. 

2.  3600 PSI, 4.3 GPM triplex ceramic plunger pump. 

3.  Manually operated unloader/bypass valve provides variable pressure 

settings up to 3600 PSI MAXIMUM.  Bypass is directed back to the 

inlet side of the pump. 

4.  Stainless steel liquid-filled gauge for accurate readings. 

5. 

¼

 turn high pressure stainless steel ball valve to isolate output 

pressure. 

6.  High pressure needle valve assembly for bleeding of air and loss 

definition. 

7. 

½

” X 8’ high pressure discharge hose. 

CONNECTING THE PUMP:

 

1.  Check oil level in pump with dip stick provided.  Use detergent 

30 wt. oil as needed. 

2.  Connect a sound 

¾

” or larger hose to the female hose swivel on the 

inlet side of the pump.  Pump requires a clean water supply.  It is 

recommended that the unit be pressure fed.  If pump is suction or 

gravity fed, the water source should be located as close to the 

pump as possible, 6-8 ft. maximum.  

3.  Connect the high pressure hose supplied to the pump and the line to 

be tested.  One end has a swivel fitting for easy hook-up.  The 

line to be tested should already be filled with water. 

4.  Open 

¼

 turn ball valve on outlet side of pump. 

5.  Slightly open needle valve on outlet side of pump to relieve air 

from piping assembly.  Close when water flows freely after opening 

supply line. 

6.  We recommend using a GROUND FAULT CIRCUIT INTERRUPTER (G.F.C.I.), 

it could save your life. 

OPERATING THE PUMP:

 

1.  Open the supply line feeding the pump or insure that suction hose 

is below water level in supply tank. 

2.  Turn motor on by engaging switch on the switch box. 

PAGE 1 OF 3 