Pag. 17 a 83
0MLMHTK65RUENUB
1.1.2
Connection of Power Cables for Single input Unit
Connect the input, output and battery cables to the terminals as shown in the figure below:
UPS 65-80kVA Power connection Terminals
Note: For the Input, Output and Battery connections, respect the order from the top to bottom, or right to left, as
described in the boxes. The label marked “N” present on the terminal identifies the neutral terminal.
The single input is a factory default configuration. Do not remove the bypass jumper. The input phase connections
are made using bolts to one of the three holes in the bus bar. Do not loosen the bolts that attach the bus bar.
Bond: The UPS is provided with a separate bus bar that connects the Neutral Output to the frame Ground for delta
input connection. This is required to meet NEC grounding code for separately derived neutrals. When a Neutral is
provided in a Wye configured input connection the bus bar must be removed.
Once installation has been completed inside the equipment, put the switch cover panel back and close the door.
Battery Input
+
-
Ground
Mains / Bypass
Input
C
B
A
Neutral Input
Bond
Load Output
C
B
A
Neutral
Output