20141167
18
GB
Installation
5.9
Gas feeding
5.9.1
Gas feeding line
Key (Fig. 14)
1
Gas input pipe
2
Manual gate
(under the responsibility of the installer)
3
Gas pressure gauge
(under the responsibility of the
installer)
4
Filter
5
Gas pressure switch
6
Safety valve
7
Pressure stabiliser
8
Adjustment valve
M1 Test point for measuring the power supply pressure
M2 Test point for measuring pressure at the head
5.9.2
Train electrical supply
The gas train supply cables can be fed to the right or left of the
burner (Fig. 15).
Depending on the entry point, the cable clamp with pressure test
point (1) and simple cable clamp (2) may need swapping over.
Consequently, you must make sure:
the cable clamp (1) is positioned correctly;
the tube is positioned correctly so that there are no
restrictions likely to impede air flowing to the pressure
switch.
Explosion danger due to fuel leaks in the
presence of a flammable source.
Precautions: avoid knocking, attrition, sparks and
heat.
Make sure the fuel shut-off valve is closed before
performing any operation on the burner.
ATTENTION
The fuel supply line must be installed by qualified
personnel, in compliance with current standards
and laws.
Fig. 14
M2
1
2
3
M1
5
6
7
4
8
D5209
ATTENTION
If necessary, cut the tube to the right size.
Fig. 15
2
1
2
1
D7113