7.3 Installing coupling
·
Remove the elastic intermediate ring (Figure
3, pos. 1).
·
Clean the borehole of the flange hub and the
shaft end before installing. The surfaces must
be clean, dry and grease-free.
·
Use suitable installation aids and hoists such
as cranes or pulley blocks in the case of
bigger couplings.
·
Pull the pre-mounted coupling halves in the
intended position on the shaft ends (Figure 3,
pos. 2).
Reference:
For easier installation a uniform warming of the hub to 80 °C to 120 °C is safe.
§
Warning!
§
Only work with gloves as a protection against hot parts of the
coupling!
·
Mount the hub so that the shaft ends
are flush with the interior borehole
opening (Figure 4).
Pay attention to possible differing
agreements!
·
Secure possible available setscrews
by tightening with an adhesive e.g.
Loctite 222 against automatic loosen-
ing and flying out.