Setting the operating pressure
1. Remove the gas control test point screw and connect the positive manometer hose.
2. Press the heater ON/OFF button to start the heater.
3. Press the ‘Test’ button twice, the heater will light to the main burner on its lowest setting
(stage 1) and the display will show PL.
4. Press the ‘Up’ and ‘Down’ buttons to set the pressure for the appropriate gas type in
accordance with the data plate. Press the ‘Set’ button once to save the setting.
5. The display will show PH (main burner stage 7). Press the ‘Up’ and ‘Down’ buttons to set the
pressure for the appropriate gas type in accordance with the data plate. Press the set button
once to save the setting.
6. The display will show 7. If the display does not change to 7 then there is an error in the
commissioning and it should be carried out again.
7. Press the ON/OFF button to stop the heater.
8. Commissioning is now complete. Remove the manometer hose and replace the gas control
test point screw.
Appliance test point pressure
Pilot pressure
test point
Pilot pressure
Inlet test point