Combination
Master
1. DET-AC III
Slave
2. DET-AC III
Slave
3. DET-AC III
Slave
4. DET-AC III
Slave
DET-AC III Master
or EFD III,
not networked
DET-AC III Master
or EFD III
combined with
1 x
DET-AC III Slave
DET-AC III Master
or EFD III
combined with
2 x
DET-AC III Slave
DET-AC III Master
or EFD III
combined with
3 x
DET-AC III Slave
DET-AC III Master
or EFD III
combined with
4 x
DET-AC III Slave
Tab. 2: Addressing S6 and S7
6.3.6.4
Connecting the energy supply and data line
1.
Connect the mains supply (Fig. 58/2) of 100 – 240 V/AC to the Master
2.
Establish the power supply (Fig. 58/5) between Master and first Slave
Chapter 5.3.7 “Power supply” on page 34
3.
Establish the power supply (Fig. 58/6) between first Slave and next Slave
4.
Ensure that there is no fire message pending at the Master.
5.
Connect the
CAN bus connecting cable (Master/Slave)
Master and first Slave.
Assembly and installation
Operating Instructions / DET-AC III Master / 916005 / 11-2022 / en_US
61