6 Commissioning
EN
6
Commissioning
Observe the aforementioned waiting period of at least
30 minutes before commissioning the unit after as-
sembly.
Remove the protective film from the red lug on the dis-
play.
Next, switch on the voltage supply to the cooling unit.
All segments in the 7-segment display will be illuminated
in sequence, followed a short time later by the start
screen.
You can now make your individual settings on the de-
vice, such as setting the temperature (see section 7
"Operation").
Note:
The oil must collect in the compressor in or-
der to ensure adequate lubrication and cool-
ing. For this reason, do not operate the
cooling unit for at least 30 minutes after as-
sembling the equipment.
Note:
It is
not
necessary to carry out leak or pres-
sure tests on the cooling unit prior to com-
missioning. Rittal has already done this in the
factory.
Note:
When the cooling unit starts up, the current
software version appears in the display.
Before commissioning, Rittal recommends
checking the Rittal website for any software
updates.
If a more recent software version is availa-
ble, please update the cooling unit soft-
ware (see section 7.3 "Updater program").