INSTALLATION
Installation Instructions for SIS Bus Bar Systems A2MS001EN revision R05
92 / 130
Fig. 104: Positioning the support clamp for
the earthing connection
5.
Position the support clamp including the
cushioning according to the project documentation and
tight it, see Fig. 104.
Fig. 105: Marking the earthing connection
to the bus bar that it was tightened with the
correct torque
6.
Tighten the earthing connection of the bus bar
and all necessary earthing cables to the support clamp
using the correct torque (see Appendix B on page 109
for the torque list). Mark the connection that it was
tightened with torque, see Fig. 105.
7.
Check the bolt connections for earthing to make
sure they are firmly locked, and mark them with a red
paint pen to indicate they have been tightened with
torque, see Fig. 105.
Individual Earthing
………………………. Personnel:
Installation Staff
Protective Equipment:
Occupational Safety Clothing
Protective Gloves
Safety Footwear
The earthing is stipulated in the earthing diagram. The
drawings in the documentation folder show a basic
illustration of the earthing options.
…
Earth each part individually with the material
included with the delivery. The rest of the earthing
process is as described under ‘Parallel Earthing’ within
this chapter.