CHAPTER
5:
ROUTINE
INSPECTION
AND
SCHEDULED
MAINTENANCE
The purpose of this chapter is to provide the operator with the routine inspection and scheduled
maintenance information required to insure a long service life of the subject compressor. Detailed
procedures for maintenance are contained in chapter 7.
5.1
ROUTINE
INSPECTION
a.
Check that crankcase oil level is 3/4 of the way up on sight glass. Check for oil leaks.
b.
Check gauge pressures against normal operating cylinder pressures.
c.
Check cooling air flow. Verify heat exchanger fins are clean and free from blockages.
d.
Check for unusual noises or vibrations.
Danger
To prevent
FIRE,
SERIOUS
INJURY
or
DEATH
, it is the User’s responsibility to
ensure that all parts used in the oxygen contacting areas of the compressor are
cleaned for oxygen service prior to installation.
All gas piping and storage systems connected to the compressor must be oxygen
clean and constructed of oxygen compatible materials.
No attempt should be made to work on the machine without full knowledge of
oxygen equipment handling procedures and the potential hazards of
contamination.
Cleaning should be in accordance with Compressed Gas Association
publication
CGA
G
‐
4.1
, Cleaning Equipment for Oxygen Service.
www.cganet.com
Any work to be done on the compressor where the gas stream may be exposed
must be done in accordance with CGA procedures.
RIX factory oxygen cleaned parts are denoted by an “X” prefix at the
beginning of the part number. It is the User’s responsibility to maintain
the cleanliness of factory cleaned parts, and any areas of the compressor
gas stream that may be exposed to contamination during maintenance.
Assembly drawings included in this manual may not have part numbers "X"
marked and therefore should be used for assembly reference only. Refer to the
parts lists in the RIX manual when ordering all parts.
Use only oxygen compatible O-ring grease and either Viton or Teflon O-rings in
gas piping areas.
Summary of Contents for 2V3B-4.1V-P1A
Page 46: ...RIX Industries MAN 2V3B 4 1V P1 Page 37 FIGURE 1 GENERAL COMPRESSOR DETAIL 1 4 ...
Page 47: ...RIX Industries MAN 2V3B 4 1V P1 Page 38 FIGURE 2 GENERAL COMPRESSOR DETAIL 2 4 ...
Page 48: ...RIX Industries MAN 2V3B 4 1V P1 Page 39 FIGURE 3 GENERAL COMPRESSOR DETAIL 3 4 ...
Page 49: ...RIX Industries MAN 2V3B 4 1V P1 Page 40 FIGURE 4 COMPRESSION VALVE DETAIL ...
Page 50: ...RIX Industries MAN 2V3B 4 1V P1 Page 41 FIGURE 5 GENERAL COMPRESSOR DETAIL 4 4 ...
Page 51: ...RIX Industries MAN 2V3B 4 1V P1 Page 42 FIGURE 6 FIRST STAGE COMPRESSION STAGE DETAIL ...
Page 53: ...RIX Industries MAN 2V3B 4 1V P1 Page 44 FIGURE 8 SUCTION AND FIRST STAGE PLUMBING DETAIL ...
Page 54: ...RIX Industries MAN 2V3B 4 1V P1 Page 45 FIGURE 9 SECOND AND THIRD STAGE PLUMBING DETAIL ...
Page 55: ...RIX Industries MAN 2V3B 4 1V P1 Page 46 FIGURE 10 FINAL DISCHARGE PLUMBING DETAIL ...
Page 56: ...RIX Industries MAN 2V3B 4 1V P1 Page 47 FIGURE 11 CRANKCASE ASSEMBLY DETAIL ...
Page 57: ...RIX Industries MAN 2V3B 4 1V P1 Page 48 FIGURE 12 CONNECTING ROD DETAIL ...
Page 58: ...RIX Industries MAN 2V3B 4 1V P1 Page 49 FIGURE 13 CONTROL BOX ASSEMBLY DETAIL 1 3 ...
Page 59: ...RIX Industries MAN 2V3B 4 1V P1 Page 50 FIGURE 14 CONTROL BOX ASSEMBLY DETAIL 2 3 ...
Page 60: ...RIX Industries MAN 2V3B 4 1V P1 Page 51 FIGURE 15 CONTROL BOX ASSEMBLY DETAIL 3 3 ...
Page 61: ...RIX Industries MAN 2V3B 4 1V P1 Page 52 FIGURE 16 WIRING SCHEMATIC ...
Page 62: ...RIX Industries MAN 2V3B 4 1V P1 Page 53 FIGURE 17 ELECTRICAL SCHEMATIC ...
Page 65: ...RIX Industries MAN 2V3B 4 1V P1 Page 55 FIGURE 18 FLOW SCHEMATIC ...
Page 70: ...RIX P N 76 713 X76 713 DWG A8042 CUI SP CTI PROPIN ...
Page 71: ...RIX P N 76 713 X76 713 DWG A8042 CUI SP CTI PROPIN ...
Page 77: ......
Page 78: ......
Page 79: ......
Page 80: ......
Page 81: ... ǣ ...
Page 82: ... Ǥ ǣ ...