25
EN
25
14
CONNECTING PHOTOCELLS
F4ES
type photocells may be installed on both sides of the barrier at two different heights: (50 cm or 100 cm).
1. Disconnect the mains power (if applicable).
2. Switch the control unit switch to the
OFF
position (fig. 15).
3. Open the photocells, rest the base on the cabinet and use it as a drilling template.
4. Drill the barrier cabinet as shown in figure 13 and fasten the base of the photocells.
5. Route the connector cables upwards, taking care not to interfere with the movements of the automation system and through the cable conduit
indicated in figure 14.
6. Connect the photocells to the terminals
COM-FT1/FT2
as indicated in the control unit installation manual.
7. Refer to the control unit manual for the photocell settings.
8. Set the switch to the
ON
position.
9. Reconnect to mains power.
13
14
13
ADJUSTING THE MECHANICAL STOP
The figure shows the mechanical stop on a barrier installed on the left
hand side. For barriers installed on the right, perform the mirror images of
the procedures illustrated.
• Unlock the barrier (see chapter 21).
• Set the completely open and completely closed positions by adjusting
the relative mechanical stops.
• Lock the barrier (see chapter 21).
12
APERTA
OPEN
CHIUSA
CLOSE
RX
RX
TX
TX
4xØ3,25
990
490
Ø15
Summary of Contents for BI/004