Installation
- 2.16 -
PCS FS Kit
2.9.3 SDB and power supply cables connection
The Figure 15 and Figure 16 show how the connections on the two versions of the
board contained in the SDBs, respectively the SDB 12+12 (56C00646) and the SDB
3+3 (56C00651) are made.
The boards are divided into two or four dials indicated by the letters TL
1
, TR, BL, BR
corresponding to two or four cable lead-through on the SDB junction boxes.
o
The red conductors (positive) of the 05R01372 and/or 05R01373 cables
should be connected to the Wago spring terminals of the corresponding
dial.
o
The black conductors (negative) of the 05R01372 and/or 05R01373 cabling
should be connected to the Wago spring terminals in the area indicated by
the black rectangle shown in the following figure (
“
Negative
”
).
Figure 15 - SDB 12+12 connections
1
These are acronyms for Top Left, Top Right, Bottom Left, Bottom Right respectively
Summary of Contents for AGRI Mate PCS FS
Page 1: ...PCS FS Installation Operation Maintenance ORIGINAL INSTRUCTIONS ...
Page 7: ......
Page 34: ...Installation PCS FS Kit 2 13 Figure 2 Wiring diagram of the system without alternator ...
Page 36: ...Installation PCS FS Kit 2 15 Figure 2 14 ECU wiring diagram ...
Page 42: ...Installation PCS FS Kit 2 21 This page is intentionally left blank ...
Page 91: ...User s manual PCS FS Kit 3 49 This page is intentionally left blank ...
Page 94: ...Maintenance and Troubleshooting PCS FS Kit 4 3 4 4 SPARE PARTS ...
Page 99: ...Maintenance and Troubleshooting 4 8 PCS FS Kit This page is intentionally left blank ...