Step 3 - Fixing the Panel to the Wall Profile

1.  Place the Setting Blocks onto the bottom of the Panel Glass, ensuring the end marked “A” is on the glass.

2. 

Carefully lift the Panel Assembly over the Wall Profile and carefully push it until it is fully home, there must 

be a minimum of 10mm for fixing. 

3.  On the inside of the enclosure, with the 2.5mm drill bit (supplied), drill a hole into the Vertical Frame and 

Wall Profile approximately 100mm from the top and bottom and one in the centre. Drill 2 holes between 

these (5 holes in total).

•  Ensure the Panel is completely vertical (the bubble on the Spirit Level must be in the centre of the 2 lines).

4. 

Fasten the Panel to the Wall Profile using the 9mm screws supplied.

5. 

Seal the Wall Profile vertically top to bottom, both internally and externally where it meets the tiles.

IMPORTANT: Failure to carry out this stage may result in serious water damage and is not covered under 

the terms of the guarantee.

•  Allow 24 hours for the sealant to fully cure prior to using the shower.

6.  Remove the setting blocks from the bottom of the door.

NOTE: 2 people will be required to carry out these operations. Some parts are hidden for clarity reasons.

10mm

Minimum

   

Ensure the

the block is 

fitted with 

the “A” on 

the glass

   

Summary of Contents for Innov8 800

Page 1: ...ommence any drilling check there are no hidden electrical cables and or water pipes 7 No attempt should be made to re work the toughened safety glass 8 The installation of the product should be performed by two persons 9 It is strongly recommended that the walls the product is going to be installed on are vertical 10 It is strongly recommended the product is fitted on a tiled surface or similar wa...

Page 2: ...d using a good quality bathroom sealant Spray the seal and joints with the shower head and check for leaks when the silicon has cured Check the plumbing for leaks DO NOT plasterboard over the tray DO NOT grout the tiles when the enclosure has been fitted the grout may discolour the aluminium profiles Make sure the tray is installed as per the manufacturer s instructions When all of the above has b...

Page 3: ...he Tray place a bead of Bathroom Sealant not supplied the width of the Wall Profile along the tiled wall Screw the Wall Profile to the wall with 40mm Screws supplied Do not over tighten the screws into the Wall Profile as this will misshape the Wall Profile Ensure the Wall Profile stays completely vertical throughout this procedure using a Spirit Level Failure to carry out this procedure correctly...

Page 4: ... in total Ensure the Panel is completely vertical the bubble on the Spirit Level must be in the centre of the 2 lines 4 Fasten the Panel to the Wall Profile using the 9mm screws supplied 5 Seal the Wall Profile vertically top to bottom both internally and externally where it meets the tiles IMPORTANT Failure to carry out this stage may result in serious water damage and is not covered under the te...

Page 5: ...he release paper from the back of the adhesive tape which is on the underside of the Bottom Rail and place the Rail inside the Dam at the pivot side of the door 6 Press the Rail down onto the top of the tray ensuring that it is kept parallel to the outside edge of the tray and that the Dam remains in position Make sure the top of the tray is clean and free from any contaminates before applying the...

Page 6: ...her Bottom Seal measuring between the edge of the glass and where the Magnets meet Make sure the rebate end of the seal is kept for the pivot side of the door If the Seal drags over the Bottom Rail the door may need raising at the magnet side Unscrew the top 3 4 door fixing screws raise the door re drill and re fix 3 Remove the Magnets from the Door Glass Fit the Bottom Seals to the Door Glass and...

Page 7: ... on the Vertical Frame and press firmly to stick the Cover Strip to the Frame The Cover Strip should sit on top of the tray 3 The Top Cap has grooves and can be shortened by cutting along these grooves using scissors or snips adding a small amount of sealant will help keep the cap in place 4 Place the Branding Badge in a prominent position on a none moving part of aluminium Cut off here Cover Stri...

Page 8: ...embly 1 14 Bottom Rail Adhesive Tape 1 24 5 Screw Cover 1 15 Bottom Rail 1 25 6 Screw Cover Adhesive Tape 1 16 Linear Seal 1 26 7 Tube Seal 1 17 Dam Right Hand 1 27 8 Dam Left Hand 1 18 Pivot Cap Right Hand 1 28 9 Top Cap 1 19 Vertical Frame 1 29 10 Pivot Cap Left Hand 1 20 Wall Profile 1 30 If you need to replace any damaged parts please see illustration below for parts list then call Customer Re...

Page 9: ...arp instruments when cleaning the enclosure Should you experience any problems during installation please refer to the Trouble Shooting Guide or contact Customer Relations on 44 0 1325 328033 To enable customer relations to provide you with an excellent level of service it is important that you quote your product Code and Reference Number these can be found on the Guarantee card Problem Solution L...

Page 10: ...us Pivot Top Cap 1 15 RIM0246 Various End Cap 1 16 RIM0402 Green Setting Block 2 17 RGT0552 Clear Innov8 Wetroom Pivoting Panel Glass 1933 x 353 50 x 8mm 1 18 RGT0551 Clear Innov8 Wetroom Hinged Panel Glass 1933 x 327 50 x 8mm 1 19 RG0384 Clear Tube Seal 1957mm 1 20 RG0419 White Double Sided Foam Tape 3 x 9mm 1957 1 21 RG0023 Grey Linear Vertical Seal 1947 1 22 RG0405 Clear Bottom Seal 1000 1 23 R...

Reviews: