Mounting and installation
Seite 8
UPT-6012
Version 2
• Comprehensive error diagnosis over the EtherCAT
®
interface
• Booster output available for connecting a switching amplifier
• High process security through comprehensive options for evaluating the parameter data (e.g. temperature
diagnosis or heat-up time monitoring)
6
Mounting and installation
See also section 2 "General information" on page 3.
Mounting, installation and startup may only be performed by authorized persons who have received
suitable instruction and are familiar with the associated risks and warranty provisions.
The supply voltage to the machine side must lie within the permitted voltage and frequency range
of the CIRUS
®
temperature controller. Otherwise, there is the danger of a defect.
6.1
Installation notes
1. Please refer to the safety and warning notes (
“General information” on page 3.).
2. The information provided in the customized ROPEX Application Report, which is specifically prepared by
ROPEX for each application, must be observed.
3. All electrical components such as the controller, impulse transformer, and line filter, should be installed as close
as possible to the UPT sealing bar(s) in order to avoid unnecessarily long cables.
4. Connect the voltage measurement cable UR directly to the UPT sealing bar and lay it twisted to the controller
(for the UML-1 voltage measurement cable see
5. Ensure an adequate cable cross-section for the primary and secondary circuits (Ä Application Report).
6. Use only ROPEX impulse transformers or transformers approved by ROPEX. Please note the power, duty
cycle, and primary and secondary voltages (Ä Application Report).
6.2
Installation procedure
Proceed as follows to install the CIRUS
®
temperature controller UPT-6012:
1. Switch off the line voltage and the 24 VDC supply, and verify that the circuit is de-energized.
2. Mount the CIRUS
®
temperature controller on a standard top hat rail (TS35 rail according to DIN EN 50022) in
the electrical cabinet. If several controllers are mounted on one rail, the minimum clearance specified in
section 10 "Technical data" on page 53 must be allowed between them.
3. Wire the system in accordance with the instructions in section 6.1 "Installation notes" on page 8, section 6.6
"Wiring diagram (standard)" on page 13, and the ROPEX Application Report. The information provided in
section 6.1 "Installation notes" on page 8 must also be observed.
Wires used for control or measuring connections must always be laid inside the building.
4. An overcurrent protective device with a maximum rating of 10 A must be fitted when the device is installed, e.g.:
- Miniature circuit breaker to EN 60898 (B, C, D, K, or Z characteristic)
- Miniature circuit breaker to UL 489 (*) (B, C, D, K, or Z characteristic)
- Fuse gG to IEC 60269
- Class CC or Class J fuse to UL 248 (*)