background image

16

FA ROTEX Solaris DrainBack - 09/2016

x

 Installation

4

Installation

These instructions describe the solar panel fastening and the hy-
draulic connection of the pressure-less Solaris system as well as 
the associated electrotechnical measures.

All assembly information for the sub-construction or the roof 
integration of the ROTEX Solaris flat solar panels are given in the 
respective quick instructions which accompany the 

roof-mounted assembly packages

in-roof assembly packages

flat roof assembly packages

.

4.1

Transport and storage

4.1.1 Transport

The ROTEX Solaris flat solar panels are delivered on a pallet, 
wrapped in film. All industrial trucks, such as lifting trucks and 
forklift trucks, are suitable for transporting it. Other ROTEX So-
laris components are delivered packaged separately.

4.1.2 Storage

The following should be taken into account when storing ROTEX 
Solaris system components:

All components should be stored in dry and frost-protected 
rooms only.

Dismantled hydraulic components must be completely 
drained before being stored.

Components must not be stored until they have cooled down.

Current-carrying components must be permanently isolated 
from the power supply before storage (switch off fuses and 
main switches, remove cables) and must be secured against 
inadvertent restarting.

The components must be stored in such a way that persons 
are not endangered by them.

The regulations in the respective documentation for other heating 
components apply for transport and storage of these products.

All steps in these instructions are described using an 
example of a single row solar panel array with double-
sided connection (solar return flow at bottom left, solar 
inflow at top right). For double-sided connection with 

reverse hydraulic connection (solar return flow at bottom left, 
solar inflow at top left), the steps must be carried out in a similar 
way. 

The gradient of the solar panel array must always be aligned to 
the bottom connection. With same-side connection, the solar 
panel array (bottom edge) must be aligned exactly horizontal.

CAUTION!

The ROTEX Solaris flat solar panels are imper-
vious to slight mechanical loading. However, 
impact, shock and walking on them should be 
avoided.

ROTEX Solaris flat solar panels should be 
transported and stored with care in their 
original packaging only and this packaging 
should not be removed until shortly before 
installation.

ROTEX Solaris flat solar panels should be 
stored and transported flat on even and dry 
supports.
– Transport with forklift trucks or cranes is 

only allowed if on pallets.

– Up to 10 flat solar panels can be stacked 

and transported on top of each other.

Summary of Contents for H26P

Page 1: ...mpanies ROTEX Solaris Planning and installation instructions DrainBack solar system Valid for the following components Solaris V21P Solaris V26P Solaris H26P Solaris assembly packages GB Edition 09 20...

Page 2: ...ystems 7 3 3 2 System components for roof mounted systems ADM 9 3 3 3 System components for in roof systems IDM 11 3 3 4 System components for flat roof systems FDM 13 4 Installation 16 4 1 Transport...

Page 3: ...ir technical training and specialist knowledge Please read this manual carefully and thoroughly before proceeding with the installation and initial start up or modifi cation of the system Comply stric...

Page 4: ...levant accident pre vention regulations as well as the recognised safety related and occupational health rules 2 3 Use as intended The ROTEX solar system may only be used for solar supported heating o...

Page 5: ...condi tions of overvoltage category III and a residual current circuit breaker RCD with a reaction time 0 2 s Compare the mains voltage 230 V 50 Hz indicated on the nameplate with the supply voltage b...

Page 6: ...ne FLS Solaris FlowSensor flow rate measurement PS Solaris operating pump RPS4 Control and pump unit TK Solaris solar panel temperature sensor TR Solaris return flow temperature sensor TS Solaris stor...

Page 7: ...r unit of an air water heating pump Electronic control The fully electronic ROTEX Solaris R4 control unit ensures op timum utilisation of the solar heat hot water heating heating support and the obser...

Page 8: ...ble pipe clamps and connecting fittings Extension kit for feed line CON XV CON XV 80 16 42 64 L 8 m UV resistant thermally insulated feed line with integrated sensor cable pipe clamps cable connection...

Page 9: ...5j Cable tie 5k Solar panel temperature sensor 5l n Extraction tool with inserts for 15 mm and 18 mm 5o Planning and installation instructions 5p Quick instructions 5q Cable connection fitting 5r Roof...

Page 10: ...escription FIX WD 16 47 03 for corrugated roofing FIX BD 16 47 04 for folded sheet metal roofing 12h Mounting profile beam 12i Quick instructions Fig 3 13 FIX WD 12j Mounting profile beam 12k Quick in...

Page 11: ...n fitting 5e g Pipe clamps with hangar bolts 5h Single terminal block with equipotential bonding terminal 5i Single terminal block 5j Cable tie 5k Solar panel temperature sensor 5l n Extraction tool w...

Page 12: ...in strip 10g Bottom left drip off sheet 10h Bottom right drip off sheet 10i Bottom left sight guard plate 10k Bottom right sight guard plate 10l Accessory bag 10m Accessory bag 10n Locking plate 10o...

Page 13: ...al block with equipotential bonding terminal 5i Single terminal block 5j Cable tie 5k Solar panel temperature sensor 5l n Extraction tool with inserts for 15 mm and 18 mm 5o Planning and installation...

Page 14: ...exagon nut M8 6m Hexagon nut M8 with locking serration 6n Washer 6o Round head screw M8 6p Quick instructions Fig 3 22 Flat roof frame basic package FB V26P 6g 8x 6f 2x 6e 6 6 c d 6a 6p 6x 6x 10x 4x 1...

Page 15: ...ut M8 with locking serration 6n Washer 6o Round head screw M8 6p Quick instructions Fig 3 24 Flat roof frame basic package FB H26P 8 8d c 8b 8a 8g x 2 8f 8e 8p x 4 x 4 x 7 x 3 x 4 x 4 6h 6n 6k 6i 6m 6...

Page 16: ...ses and main switches remove cables and must be secured against inadvertent restarting The components must be stored in such a way that persons are not endangered by them The regulations in the respec...

Page 17: ...nting rail 2b Solar panel securing clips 4 Solar panel 5 Solar panel connecting elbow return flow 6 Solar panel connecting elbow inflow 7 Sealing plug 8 Solar return flow pipe 9 Solar inflow pipe 10 S...

Page 18: ...of the inflow pipe is not more than 16 mm a continuous rise of the inflow pipe to the highest point as well as a continuous gradient to the warm water storage cylinder is ensured For pipe runs in whic...

Page 19: ...M16 glands from inside 7 For on roof mounting Cover the roof penetrations The roof tiles at the side and above must overlap the roof penetration The corrugated flashing must overlap the roof tile und...

Page 20: ...gs such as roof tiles with very pronounced undulations large differ ences in height sealing problems can occur with the universal roof penetration box In such cases and also with plane tiles or slate...

Page 21: ...tep 3 CAUTION In order to prevent torsional stresses and fixing difficulties when mounting the solar panels slightly tighten the self locking nuts of the slide blocks align both mounting profiles exac...

Page 22: ...e system Always fit the expansion joints to the flat solar panels with extreme caution Bring the next flat solar panel in alignment with the connection pipes of the previous flat solar panel when push...

Page 23: ...Insert the sealing plugs into the open solar panel connection pipes until the retaining clamps audibly click in place These instructions only describe the pipe laying for al ternate end connection wit...

Page 24: ...sing cable ties Then connect the silicone covered cable inside the roof to the connection cable of the solar panel temperature sensor of the control and pump units WARNING The equipotential bonding do...

Page 25: ...nducted by ROTEX authorised and trained heating experts Before start up the protective conductor re sistance and proper connection must be checked CAUTION Setting up in frosty conditions can result in...

Page 26: ...al in compliance with the respective na tional regulations of the country of use is the responsi bility of the user owner Disassembly of the system handling of coolant oil and other parts may only be...

Page 27: ...EC for correct selection of products for your application contact your dealer Depending on your application and the product selected an additional supplementary heater may have to be installed Tab 6...

Page 28: ...anently standstill proof and thermo shock tested Minimum collector yield above 525 kWh m2 per year with 40 cloud coverage location W rzburg Tab 6 2 Technical Data Flat Solar Panel Unit Solaris flat so...

Page 29: ...ssible roof load has been exceeded by the ballast weight secure the solar panel array using a suitable steel rope construction Working angle Wind action kN m2 0 5 0 65 0 8 0 95 1 1 1 2 1 3 Ballast wei...

Page 30: ...5 60 6 50 7 21 7 48 7 70 3 64 4 23 4 69 4 86 5 00 50 5 11 5 87 6 46 6 68 6 85 3 32 3 82 4 20 4 34 4 45 48 4 72 5 37 5 86 6 04 6 18 3 07 3 49 3 81 3 93 4 01 46 4 41 4 97 5 38 5 53 5 63 2 86 3 23 3 50 3...

Page 31: ...ial bonding 24 Roof penetration 19 Solar panel temperature sensor 24 M Mounting profile connector 8 Mounting profile rail 7 O Operating mode 7 Outer layer of storage tank 7 P Parallel connection 17 Pr...

Page 32: ...ROTEX FA ROTEX Solaris DrainBack Subject to change and correction 008 1628844_00 09 2016...

Reviews: