2015-2017 5.0L Mustang Phase 1/2 RHD ROUSHcharger Kit
SECTION D – INSTALLATION
1316-RHD-AA 12152016
54
800.59.ROUSH
SECTION D – INSTALLATION
The following section will guide you through the fi nal
installation of the kit into the vehicle. If you need to
stop during any part of the installation, make sure
you cover any open ports in the cylinder heads or
intake manifold to prevent foreign material from
contaminating your engine.
INDUCTION RESONANCE TUBE DELETE
GROMMET
1. Obtain the induction resonance tube delete
grommet (W651016) from Hardware Kit A
(1315-TVSHKA).
2. Install the induction resonance tube delete
grommet in the hole that was exposed when the
resonance tube was removed.
NOTE:
If the ROUSH boost gauge kit is going to be
installed onto the vehicle, the above grommet can
be left out as the boost gauge kit has a pre-installed
grommet on the vacuum line that will go in this
location.
INTAKE MANIFOLD, FUEL RAILS,
SUPERCHARGER, SPACER AND
THROTTLE BODY
1. Remove the tape from the cylinder heads and
clean the cylinder head to intake manifold mating
surfaces.
2. Install the fuel charging assembly (1315-9H487)
and check to make sure it is seated completely.
If not, remove it and grind the modifi ed area in
the engine valley again until the manifold seats
properly.
Grind area if intake won’t seat
3. Install the engine harness ground wire tab at the
RH front of the intake manifold using one (1) of
the M6 x 1.0 x 40 mm bolts (R18020004) found in
Hardware Kit B (1315-TVSHKB). Do not tighten
the fastener down until the next step. Zip tie the
ground wire to the engine harness.