5. INSTALLATION
Before lifting the main ON/OFF switch (3) fill the rear water tank under the cup shelf
(11).
1)
Remove the coffee machine from its parcking and check that it has not been damaged.
2)
Place the appliance on a stable top, close to the mains sockets and water line connections.
Check that the voltage of your mains supply corresponds to that indicated in the technical specifica
-
tions.
3)
Remove the upper cover grid (11), take out the water
tank (located inside the machine) and rinse it (Photo 1).
4)
Fill the tank with approx. 3 litres clean water, put it
back, connect the water softener and insert the small
silicone tubes. Close the upper cover grid (11) on the
machine.
5)
Before start-up the fitter must make sure the ma
-
chine has been properly connected to the electrical and
earthing systems involved and check the efficiency of
protection from direct contact.
In Europe connect the approved cord H05VV-F 3G 1.5 mm with the Schuko plug to the electricity
supply.
In USA-Canada connect the approved cord Type SJTO, rated 3x14 AWG, 300 V, 105°C with the
NEMA 5x15P plug to the electricity supply.
IT IS STRICTLY FORBIDDEN TO USE THE MACHINE WITHOUT EFFEC-
TIVE SAFE EARTHING.
If the machine is new, it is advisable that you let the water circulate through the system:
turn the water knob (2) and fill a jug with at least 0.5 litres water.
5a. MACHINE WITH CONNECTION TO THE MAINS
WATER SUPPLY
If your machine is to be connected to the mains water supply call a specialized technician, who will
connect the machine inlet pipe to the water softener (not provided) using the hose (3/8’’) provided. A
pressure reducer must be installed. Switch on the water softener and check for any leaks.
6. MACHINE IGNITION
Before turning on the machine it is advisable that you check that there is water inside the
rear tank under the cup shelf (11).
1)
Lift the ON/OFF power switch (3).
The red indicator light (4) comes on.
2)
When the machine is switched on, the electronic
card checks water level inside the boiler. After ap-
prox. 3 seconds, the filling pump and solenoid valve
are enabled for filling.
The coffee machine will automatically be filled with
water up to the pre-set level (level probe inside the
boiler).
3)
When the set level is reached, the pump stops. The