2.1 Machine installation
For the transport and delivery the machine is equipped with two casters at the front and two
steering rollers with a locking brake each at the back.
For a safe transport the brakes have to be
unlocked. The operator moves the machine
in the desired direction by pushing and
steering it from the back with the hands holding
on to back with the hands holding on to
the top.
No persons or objekts should be near or in
front of the machine during transport.
During the
installation and transport of the machine
see to it that the floor can withstand a
load of 400 Kg/m². The machine has to be positioned in such a way that a passable safety path
of one meter in width is all around the machine.
No objects, which could change the centre of gravity or the total weight should be lying on the
machine during transport.
The two locking brakes have to be
engaged once the desired process
location has been reached.
Check the structure and the slope of the
floor in order to guarantee a save position
of the machine.
The machine has to be positioned in such a way, that there is an unrestricted ceiling height of at
least 2,30 m so that the operator has an unrestricted working area above the machine.
2.2 Connection of the machine
Before connecting the machine to the mains, make sure that the power outlet is dimensioned
according to the machine datas. The High-Tech-Cutter SR1 and SR1 turbo is standard equipped
with a connected load of 400 V / 50 Hz / 16 A / 1,5 kW.