Once the softener is programmed you can now start passing water through the 
unit   

 

Fill the Cabinet brine tank with water approx. 25mm above the salt 
platform 

 

Add at least two bags of salt to the platform  

 

Put the softener into Regeneration 

 screen will display -00- this is the 

valve moving into the backwash cycle, once this has stopped the 
backwash symbol will be displayed          and the minutes will start 
counting down. 

 

Slowly open the inlet water connection a ¼ turn to allow a small flow of 
water into the softener to releasing air out of the cylinder 

 

Once all the air has been removed from the cylinder you can now open 
the inlet valve fully to clean the resin bed 

 

When the water is running clear press the regen button again to skip to 
the next cycle 

 

The valve will now be in Brine draw cycle, press the regen button again 
to skip to brine refill 

 

Allow the valve to top up the brine tank to the required level for a salt 
solution  

 

Once refill has completed leave the valve to complete the regeneration 
process and rinse the resin bed 

 

 

 

 

 

 

 

 

 

 

Summary of Contents for 41-S150

Page 1: ...Page 1 of 12 CABINET WATER SOFTENER RUNXIN VALVE PROGRAMMING PROCEDURE Models Cabinet Softener RL R150 F69P3 F70BL 74602 ...

Page 2: ...Page 2 of 12 Valve Buttons Valve Configuration ...

Page 3: ...outlet 3 4 F Drain 1 2 M Brine line connector 3 8 M Base 2 5 8NPSM Riser pipe 1 05 OD Resin Amount 28Lts Water treatment capacity 2 m h Tank diameter 10 x 35 Water pressure 0 15MPa 0 6MPa Water temperature 5 38 Water turbidity Up flow regeneration 2FTU Power adapter Input AC100 240V 50 60Hz Output DC12V 1 5A ...

Page 4: ...Page 4 of 12 Button Operation Menu Confirm Start Regeneration Skip Regeneration Cycle Return Down Up Valve Locked Press Simultaneously for 5 secs to unlock the screen ...

Page 5: ...Page 5 of 12 Control Valve Symbols Backwash Brine Draw Brine Refill Fast Rinse Settings Clock Days until Backwash Controller Locked ...

Page 6: ...r with constant power out the GPO Water pressure not to exceed 600kPa with a minimum pressure required of 0 15kPa Easily accessible for maintenance of the unit Add salt to the brine tank Installation Connect the inlet and outlet pipework as per the directional arrows on the back of the water softener valve Female BSP connections Run the drain line to an open drain line an air gap is required to pr...

Page 7: ...or 5 secs until you hear a beep Press the Menu Button Press the Down arrow Press Menu The hour will then flash change the Hour time to desired time by pressing the up or Down button press Menu to save The minutes will then flash Change the minutes time with the up or down arrow and press menu to confirm changes Regenerate on 0m Capacity or at Regeneration Set Time Unlock Valve Press Up Down arrow ...

Page 8: ... of days by pressing the up or Down button press Menu to save Set Water softener Capacity Unlock Valve Press Up Down arrow together for 5 secs until you hear a beep Press the Menu Button Press down arrow four An hourglass and a m symbol will light up Press Menu Button The digits will then flash change the number to the amount of capacity estimated for the ion exchange process in litres the softene...

Page 9: ...et Press down The Hourglass and the Brine Draw symbol will light up press menu the time will flash press the up and down arrows to change to 49mins Press menu to confirm Brine Refill Once Brine Draw is set Press down The Hourglass and the Brine Refill symbol will light up press menu the time will flash press the up and down arrows to change to 7mins Press menu to confirm Fast Rinse Once Brine Refi...

Page 10: ... down Slowly open the inlet water connection a turn to allow a small flow of water into the softener to releasing air out of the cylinder Once all the air has been removed from the cylinder you can now open the inlet valve fully to clean the resin bed When the water is running clear press the regen button again to skip to the next cycle The valve will now be in Brine draw cycle press the regen but...

Page 11: ... media material through drain line a Air in the system b Backwash flow control to high c Top screen broken a Bleed air from the system Check for leaks b Reduce Backwash flow to suitable size c Check and replace top screen Control valve cycle continuously a Wrong size transformer b Foreign material stuck in drive gear c Faulty valve a Use correct Transformer b Remove Foreign material from drive gea...

Page 12: ...rd and display board failure b Locating board damaged c Mechanical driver fails d Faulty control board e Wiring between the control board and motor fault f Motor damaged a Replace the wiring between display board and locating board b Replace locating board c Check and repair mechanical part d Replace control board e Replace wiring between control board and motor f Replace motor E2 Flash a Componen...

Reviews: