Photoelectric

Smoke Detector

TYPICAL WIRING DIAGRAM 

Figure 1.a shows the typical wiring diagram of 2-wire 

multiple-station smoke detector system. 

DO NOT USE LOOPED WIRE UNDER 

TERMINALS 2 AND 5 BREAK WIRE RUN TO 

PROVIDE SUPERVISION OF CONNECTIONS 

Figure 1.b shows the typical wiring diagram of 4-wire 

multiple-station smoke detector system.

DO NOT USE LOOPED WIRE UNDER 

TERMINALS 2 AND 5 BREAK WIRE RUN TO 

PROVIDE SUPERVISION OF CONNECTIONS 

WARNING

TO  PREVENT  DETECTOR  CONTAMINATION 

AND 

SUBSEQUENT 

WARRANTY 

CANCELL

A

TION, 

T H E  

SMOKE 

DETECTOR  MUST  REMAIN  COVERED 

UNTIL  AREA  IS  CLEAN AND DUST   FREE. 

INSTALLING THE BASE 

1.

 To insure proper installation of the detector

,

 head to 

the

 

base,  all  the  wires  should  be  properly 

addressed  at

 

installation:

(A) 

Position all the wires flat against terminals.

(B) 

Fasten the wires away from connector terminals.

2.

 If  you  use  the  jumper  wire  to  connect  the  poles  of

 

terminal  2  and  5  when  testing  the  detector 

loop

's 

continuity, be sure to remove the jumper wire 

prior to

 

the installation of the detector head.

3.

 The  end-of-line  device  shown  in  Figure  1.a  &  1.b

 

should  be  compatible  with  the  control  unit.  The

 

end-of-line supervisory relay used should list the rated

 

DC power voltage used.

4.

 Per  UL  listing,  open  area  smoke  detectors  are

SF119 series 

Installation Wiring Diagram

intended  for  mounting  on  a  ceiling 

at  least

  6  inches 

away 

from a wall or mounting on a wall 

between 

and 

12 inches 

away 

from a ceiling. 

5. The base of smoke detector can be mounted directly

onto 

an 

electrical  junction  box

:

  octagonal  (3”,  3.5”

 

or 

4”),  round  (3”),  and  square  (4”  length)  box

es

  without

 

using any type of mechanical adapter

s

.

INSTALLING THE HEAD 

1.

Align the components as shown in Figure 2.

2.

Mate the detector head onto the base and twist

 it 

clockwise to secure it.

3.

Do  not  install  the  detector  head  until  the  area  is

 

thoroughly  cleaned  of  construction  debris,  dusts,  etc.

 

The  maximum  number  of  smoke  detector  installed  in

 

the same loop is 30 units.

Fig. 2 Mating detector head onto base 

ADJUSTMENT OF THE RELAY POSITION 

4-wire type: Adjust the relay set-position for wiring unit to

 

the 

security monitoring system 

through

 the following steps:

1. The  reset  position  for  the  relays  is  “normal

ly

 open”

(NO), when 

powering

 all the relays.

2.

3.

 

T

o  adjust  the  relay  set  point,  use  a

 

screwdriver  to 

loose

n the

 two  screws  on  the  back  of  the

 

base.

 

Figure 3

 shows 

a jump head next to the

 

relay  on  the 

PCB,  adjust  it  to  select  either

 the

 

“normal

ly

 

close

d

” (NC) or 

the 

“normal

ly

 open” (NO) position

s

.

 

 

Relay contact rating:

1A @30VDC,

0.5A @125VAC.

TESTING

1.

All  the  alarm  signal  services,  releasing  device  and

 

extinguisher system should be disengaged during the

 

test period and must be re-engaged immediately at the

 

conclusion of testing.

2.

After 

powering

 the  detector  head  for  approximately

 

one  minute,  check

  if  the

 red  LED

 light is

 

flashing 

once  every  1~3  seconds.  If 

the 

red  LED  fails  to

 

flash, it indicates 

that 

the detector

 is not functioning 

properly

 or

 

the possibility of having incorrect 

wiring. 

Re-check  the  wiring  or  replace  the

 

detector if 

necessary.

Fig. 3 Schematic of detector structure 

     When front cover is open   