14
1. All electrical components and connections must be installed by a licensed electrician in accor-
dance with local, state, and federal regulations and code.
It is the responsibility of the owner or
installer to determine local, state, and federal code and regulations prior to installation
.
2. Be sure to check all connections, and verify GFCI operation before completing installation of
bathtub.
3. If your So-Lo was ordered with the optional heated shower deck, it comes with a pre-installed
deck surface warmer. The electrical for this system must be roughed in at this time. Safety
Bath recommends a 15-Amp 30-minute timer switch be mounted in a convenient location near
the bathroom’s light switch in accordance with local and federal code to supply 120VAC to the
deck warmer. This circuit must be a dedicated 15A GFCI circuit. Refer to illustration on this
page showing the location of the 120VAC/24VAC transformer, as well as the wiring schematic on
the next page.
4. If your So-Lo was ordered with the optional 12-Jet Warm Air Massage hydrotherapy system, a
dedicated 15A GFCI circuit must be roughed in from the breaker panel to the bathtub location.
Refer to the illustration on this page showing the location of the bathtub’s blower motor assem-
bly, as well as the wiring schematic on the next page. The electrician must install a waterproof
electrical junction box (not included) to make the connection between the building’s supply wire
and the blower motor wire.
Heated Shower Deck
Transformer
Warm Air Massage System
Blower Assembly
Waterproof Electrical
Junction Box
—- Not Included —-
** Refer To Local, State, & Federal Code **