LIFT MODEL VISION AS 300 Rev001
7-2
ATTENTION:
To mount elements having heavier weight than 30 kg per person
use a lifting device.
ATTENTION:
During the erection and the dismantling stages the wind blowing
speed cannot be higher than 45,7km/h (12,7m/s).
7.2
Safety prescriptions
•
The erection and disassembly of lift must always be done under the strict
supervision of one of the yard technicians and performed by competent and
specifically trained personnel only.
•
During the erection, dismantling and use, the transiting and waiting under or in the
nearby of the lift will have to be forbidden by using special signaling and fence
•
The lift will never have to be loaded with heavier weight than those specified in this
manual.
•
All the erection/dismantling, safety, maintenance and electric rules established in
this manual must not be broken nor the laws in force.
•
Every elevator is provided with its relative manual which must be kept in the same
place where the elevator is used.
•
During the erection and the dismantling stages the wind blowing speed cannot be
higher than 45,7km/h (12,7m/s).
•
To mount elements having heavier weight than 30kg per person use a lifting device.
•
Follow carefully the instructions and use the same sequence given here to follow.
7.3
Machine transport
The motor group, the cabin and the base with the first mast element of the lift can be supplied
together or separately, in case of problems with the dimensions during transport and erection.
The assembly of the parts will be carried out in the building yard at the time of installation.
7.4
Unpacking
The machine is packed and strapped up; electric and fragile parts can be protected by a sheet
in nylon until the delivery.
Remove the nylon sheet, if present, taking care to keep it out of reach of children; dispose of the
packing using the special containers for the differentiated refuse collection.
Remove the iron strings, wrap them up before eliminating them, and do not leave pieces of
strings around, especially in the vicinity of the place of use of the machine.
After the machine unpacking, check that:
•
the machine has not been damaged before the delivery, advice immediately the
seller before use of the machine;
•
all the parts of the machine are present (bolts and nuts, electric installation, etc.) and
according to the specifications of the supply;
•
if any missing parts from the order placed; In case of modifications, these must not
preclude the use or modify the criterion of use of the machine, and must have been
agreed by the manufacturer and specified in the manual of use.
Summary of Contents for VISION AS 300
Page 2: ......
Page 4: ......
Page 43: ...LIFT MODEL VISION AS 300 Rev001 7 4 Fig 7 1 Dimension...
Page 68: ...LIFT MODEL VISION AS 300 Rev001 12 1 12 WIRING DIAGRAMS Fig 12 1 Wiring diagram Power supply...
Page 69: ...LIFT MODEL VISION AS 300 Rev001 12 1 Fig 12 2 Wiring diagram Motor power supply...
Page 70: ...LIFT MODEL VISION AS 300 Rev001 12 2 Fig 12 3 Wiring diagram Emergency circuit...
Page 71: ...LIFT MODEL VISION AS 300 Rev001 12 3 Fig 12 4 Wiring diagram Auxiliary...
Page 72: ...LIFT MODEL VISION AS 300 Rev001 12 4 Fig 12 5 4 Wiring diagram Auxiliary PLC logo expans...
Page 73: ...LIFT MODEL VISION AS 300 Rev001 12 5 Fig 12 6 Auxiliary circuit...
Page 74: ...LIFT MODEL VISION AS 300 Rev001 12 6 Fig 12 7 Wiring diagram Connectors C1 C2 C3...
Page 75: ...LIFT MODEL VISION AS 300 Rev001 12 7 Fig 12 8 Wiring diagram Terminal box electric panel...
Page 76: ...LIFT MODEL VISION AS 300 Rev001 12 8 Fig 12 9 Wiring diagram Cable call floor...
Page 77: ...LIFT MODEL VISION AS 300 Rev001 12 9 Fig 12 10 Wiring diagram Floors call connection...
Page 78: ...LIFT MODEL VISION AS 300 Rev001 12 10 Fig 12 11 Wiring diagram Box floor call connection...
Page 79: ...LIFT MODEL VISION AS 300 Rev001 12 11 Fig 12 12 Wiring diagram Box Fencing connection...
Page 80: ...LIFT MODEL VISION AS 300 Rev001 12 12 Fig 12 13 Wiring diagram Cable fancing call...
Page 81: ...LIFT MODEL VISION AS 300 Rev001 12 13 Fig 12 14 Main electrical box components...
Page 82: ...LIFT MODEL VISION AS 300 Rev001 12 14 Fig 12 15 Material list 1...
Page 83: ...LIFT MODEL VISION AS 300 Rev001 12 15 Fig 12 16 Material list 2...