In case of electric power supply failure during the mounting
dismantling phases of the mast, with a consequent stop of the elevator
with personnel on board high from the ground, it is possible to descent
to the floor or to the nearest point by operating the gear motor brake.
ATTENTION:
Emergency manual descent.
ATTENTION:
Now the elevator is ready to regular use for serving persons and
material according to the characteristics of use described in
chapter
USE
!
ATTENTION:
Test every 15 days the tightening of the mast bolts and of the
anchorages clamps!
7.12
Dismantling
ATTENTION:
Check the tightening of mast bolts and anchorages clamps rising
upward until reaching the summit!
ATTENTION:
Make sure that during the dismantling stages of the mast the
working deck underneath is absolutely free from people and
properties who/which would be injured/damaged in case of fall of
parts of the machine!
1
Remove the multiple six-pole plug of the floor landing doors line and insert the plug
of the push-button panel, which allows the control of the lift during the mounting and
dismantling.
60. Remove the electric installation of the call to the floors.
61. Once the summit is reached, proceed in sequence to the dismantling of the
mast
and
the floor landing doors. The mast must be loaded into the cabin, taking care not to
exceed the nominal capacity load of the hoist
ATTENTION:
the operators on top of the hoist must work with the safety harness
on and hitched!
62. Proceed in sequence to the dismantling of the floor landing doors.
63. Make sure that the access to the floors have been adequately fenced.
64. Go down to ground level for the unloading phase of the mast, of the floor landing doors
(if any) and of the anchorages.
65. Reach to the highest point of the mast to start the disassembly.
66.
During the mounting and dismantling operations
Signal by means of adequate warning
signs, applied inside the hoist way, the admittance to an elevator and the possibility to
fall into the hoist way.
NOTE:
of the mast modules, it is recommendable to lash them to a safety rope and
to release them only after the fastening of the bolts and nuts.
67. Remove other mast and load them in the cabin, then go down to ground level for the
unloading phase.
68. Rise up again and remove the anchorage and other masts. Repeat this sequence of
operations until reaching the base with the elevator car and until the first mast only
remains.
69. Once arrived to ground level cut off the power to the hoist.
70.
Demount
the fence doors with their counterweights.
Summary of Contents for VISION AS 300
Page 2: ......
Page 4: ......
Page 43: ...LIFT MODEL VISION AS 300 Rev001 7 4 Fig 7 1 Dimension...
Page 68: ...LIFT MODEL VISION AS 300 Rev001 12 1 12 WIRING DIAGRAMS Fig 12 1 Wiring diagram Power supply...
Page 69: ...LIFT MODEL VISION AS 300 Rev001 12 1 Fig 12 2 Wiring diagram Motor power supply...
Page 70: ...LIFT MODEL VISION AS 300 Rev001 12 2 Fig 12 3 Wiring diagram Emergency circuit...
Page 71: ...LIFT MODEL VISION AS 300 Rev001 12 3 Fig 12 4 Wiring diagram Auxiliary...
Page 72: ...LIFT MODEL VISION AS 300 Rev001 12 4 Fig 12 5 4 Wiring diagram Auxiliary PLC logo expans...
Page 73: ...LIFT MODEL VISION AS 300 Rev001 12 5 Fig 12 6 Auxiliary circuit...
Page 74: ...LIFT MODEL VISION AS 300 Rev001 12 6 Fig 12 7 Wiring diagram Connectors C1 C2 C3...
Page 75: ...LIFT MODEL VISION AS 300 Rev001 12 7 Fig 12 8 Wiring diagram Terminal box electric panel...
Page 76: ...LIFT MODEL VISION AS 300 Rev001 12 8 Fig 12 9 Wiring diagram Cable call floor...
Page 77: ...LIFT MODEL VISION AS 300 Rev001 12 9 Fig 12 10 Wiring diagram Floors call connection...
Page 78: ...LIFT MODEL VISION AS 300 Rev001 12 10 Fig 12 11 Wiring diagram Box floor call connection...
Page 79: ...LIFT MODEL VISION AS 300 Rev001 12 11 Fig 12 12 Wiring diagram Box Fencing connection...
Page 80: ...LIFT MODEL VISION AS 300 Rev001 12 12 Fig 12 13 Wiring diagram Cable fancing call...
Page 81: ...LIFT MODEL VISION AS 300 Rev001 12 13 Fig 12 14 Main electrical box components...
Page 82: ...LIFT MODEL VISION AS 300 Rev001 12 14 Fig 12 15 Material list 1...
Page 83: ...LIFT MODEL VISION AS 300 Rev001 12 15 Fig 12 16 Material list 2...