The use of the lift must follow an accurate reading of the following paragraphs; in case of
doubts on how the lift operates or for any fault found consult immediately, before the use, the
assistance service or the manufacturer!
The elevator must be used in conformity with the prescriptions provided by this manual - any
other way of use is not allowed.
The elevator can be used to lift persons and materials until the maximum weight, uniformly
distributed onto the elevator, equals to 300 kg.
ATTENTION:
The use of the elevator is forbidden to load unauthorized persons,
overhanging loads, material not properly secured and loose
material.
ATTENTION:
The elevator cannot be used in unsuitable and adverse weather
conditions.
ATTENTION:
The
lift
cannot be tampered, spare parts must be original.
DANGER:
The elevator cannot be used if the stop safety devices have not been
fitted (limit switches), scheduled maintenance have not been carried
out and when the anchorages are precarious.
ATTENTION:
SAFI does not assume responsibility for any injury to people or
domestic animals or damage to properties arising from the non-
observance of the precautions given.
Responsibilities of the user
a) – Use of the lift is allowed only to qualified personnel trained on its use and informed
about safety devices and regulations.
b) – The operators should act with the maximum attention, to be
physically
fit and not
under the influence of alcohol or drugs/sedatives which could compromise hearing,
sight and attention level and/or reaction time.
c) - The operators should give priority to the safety and refuse to operate when they think
the safety conditions do not correspond to what stated in the directives.
d) - Operators should verify and prohibit the presence of persons, animals, devices or
materials from being in dangerous zones or in the lift operating area.
Safety rules
The
lift
must be well anchored to the ground, follow the erection operations description in
chapter
ERECTION AND DISMANTLING
.
A- Maneuvering of the platform is allowed to personnel expressly trained and entrusted with
this task only.
B- The
lift
use must be forbidden to unauthorized personnel, acting on the padlock of the
cut-out switch on the control board.
C- The elevator must never be overloaded, respect the loads allowed specified in this
manual.
D- When an imminent or actual danger arises, press immediately the emergency button on
the control panel. Lift movement will stop immediately.
Summary of Contents for VISION AS 300
Page 2: ......
Page 4: ......
Page 43: ...LIFT MODEL VISION AS 300 Rev001 7 4 Fig 7 1 Dimension...
Page 68: ...LIFT MODEL VISION AS 300 Rev001 12 1 12 WIRING DIAGRAMS Fig 12 1 Wiring diagram Power supply...
Page 69: ...LIFT MODEL VISION AS 300 Rev001 12 1 Fig 12 2 Wiring diagram Motor power supply...
Page 70: ...LIFT MODEL VISION AS 300 Rev001 12 2 Fig 12 3 Wiring diagram Emergency circuit...
Page 71: ...LIFT MODEL VISION AS 300 Rev001 12 3 Fig 12 4 Wiring diagram Auxiliary...
Page 72: ...LIFT MODEL VISION AS 300 Rev001 12 4 Fig 12 5 4 Wiring diagram Auxiliary PLC logo expans...
Page 73: ...LIFT MODEL VISION AS 300 Rev001 12 5 Fig 12 6 Auxiliary circuit...
Page 74: ...LIFT MODEL VISION AS 300 Rev001 12 6 Fig 12 7 Wiring diagram Connectors C1 C2 C3...
Page 75: ...LIFT MODEL VISION AS 300 Rev001 12 7 Fig 12 8 Wiring diagram Terminal box electric panel...
Page 76: ...LIFT MODEL VISION AS 300 Rev001 12 8 Fig 12 9 Wiring diagram Cable call floor...
Page 77: ...LIFT MODEL VISION AS 300 Rev001 12 9 Fig 12 10 Wiring diagram Floors call connection...
Page 78: ...LIFT MODEL VISION AS 300 Rev001 12 10 Fig 12 11 Wiring diagram Box floor call connection...
Page 79: ...LIFT MODEL VISION AS 300 Rev001 12 11 Fig 12 12 Wiring diagram Box Fencing connection...
Page 80: ...LIFT MODEL VISION AS 300 Rev001 12 12 Fig 12 13 Wiring diagram Cable fancing call...
Page 81: ...LIFT MODEL VISION AS 300 Rev001 12 13 Fig 12 14 Main electrical box components...
Page 82: ...LIFT MODEL VISION AS 300 Rev001 12 14 Fig 12 15 Material list 1...
Page 83: ...LIFT MODEL VISION AS 300 Rev001 12 15 Fig 12 16 Material list 2...