4.  ON/OFF SEQUENCE.

Danger of electric arc. Do not open any DC isolator switches if the device is charging.

Follow the steps below in order to start up the inverter:

1. 

Activate the inverter’s isolator switch and place it in the ON position.

2. 

Make sure the solar park is connected. Activate the protections in order to enable the photovoltaic supply.

3. 

Make sure there is mains voltage. Activate the protections in order to enable the mains supply. Without a mains supply, the device 

will not enter generation mode.

AC

DC

4. 

The device will start up. The LCD screen will turn on. The following section details the steps to follow and explains how the console 

works.

Follow the steps below in order to stop the inverter and switch it off:

1. 

Shut off the mains power supply. Without a mains supply, the device will stop generating.

2. 

Shut off the solar park power supply. Activate the protections in order to shut off the photovoltaic supply.

3. 

Deactivate the inverter’s isolator switch and place it in the OFF position.

AC

DC

OFF

ON

ON

4. 

The device will stop. When the internal capacitors of the DC bus are without voltage, the LCD screen will turn off.

Summary of Contents for EQUINOX EQX 10000-2T

Page 1: ...EQX 5000 2T EQX 8000 2T EQX 10000 2T SOLAR INVERTERS QUICK GUIDE ...

Page 2: ...2 SALICRU ...

Page 3: ... 3 ELECTRICAL INSTALLATION 3 1 DC DIRECT CURRENT INSTALLATION 3 2 AC ALTERNATING CURRENT INSTALLATION 3 3 JUNCTION BOX 4 ON OFF SEQUENCE 5 OPERATION USING THE DISPLAY 5 1 DISPLAY 5 2 PARAMETERS MENU 5 3 DISPLAY LED INDICATORS 5 4 FAULT CODES 6 SMARTPHONE APP 6 1 DOWNLOADING AND INSTALLING THE APP ON YOUR SMARTPHONE ...

Page 4: ...mount 1 4 Metal bolt only for concrete walls 4 5 Fixing screws 2 6 POSITIVE DC connector set and terminal 2 7 NEGATIVE DC connector set and terminal 2 8 AC connector 1 9 RS485 communications connector 1 If anything is missing contact your supplier in order to return this device and arrange for a new one containing all of the listed items to be delivered ...

Page 5: ...der to avoid extending the RS485 communications cable Angle and spacing of the installation Make sure the device is installed on a vertical surface and that the following minimum safety distances are maintained with regard to other elements in order to ensure optimum ventilation Dimension Distance mm A 500 B 400 Wall mount 5 10 kW Model A mm B mm Ø mm Drill depth mm Tightening torque Nm EQX 5000 2...

Page 6: ...6 SALICRU Mounting process Material required Steps to follow ...

Page 7: ... and that there is no voltage in the cables you are going to handle DC Connecting the solar park cables Material required 1 Unscrew the MC4 connectors supplied and prepare the cables coming from the junction box of the solar park 2 Pass the cables through the screw caps crowns and rubber seals as shown below Then crimp the metal terminals to the cables To ensure an optimum connection use an approv...

Page 8: ...mum tightening without damaging the connectors 5 Check the polarity and voltage of the photovoltaic panels before connecting them to the inverter in line with the values shown in the following table Specifications Inverter model EQX 5000 2T EQX 8000 2T EQX 10000 2T Maximum DC input power W 5500 8800 11000 Maximum DC input voltage VDC 900 1000 Operating range VDC 200 800 MPPT range VDC 260 800 350 ...

Page 9: ...nt lengths If the facility s solar panels are not on the same level i e they are exposed to different levels of radiation whether due to the shape of the roof differences in inclination or different string lengths the connection process must be carried out as follows The devices allow for a maximum solar power imbalance of 40 60 Connection process for facilities with a single solar park i e panels...

Page 10: ...Strings that can be connected to each MPPT depending on the device model Model String MPPT EQX 5000 2T 1 2 EQX 8000 2T 1 2 EQX 10000 2T 1 2 3 2 AC ALTERNATING CURRENT INSTALLATION Make sure the protection systems in the junction box are activated and that there is no voltage in the cables you are going to handle If you are installing the optional ESM3T EQX energy meter we recommend installing the ...

Page 11: ...rminals at the ends of the cables 3 Insert and screw the cables to the corresponding terminals on the connector R phase S phase T phase and earth G Once this is done pull gently on the cables to make sure they are firmly attached 4 Connect the sleeve to the inverter s AC connector 5 Connect the other end of the sleeve to the AC protection in the junction box 6 Connect the AC part of the junction b...

Page 12: ... 1000 VDC 15 A string Type II 40 kA 1000 VDC Type I II 5 kA 1000 VDC EQX 8000 2T Built into the device Fuses 1000 VDC 15 A string Type II 40 kA 1000 VDC Type I II 5 kA 1000 VDC EQX 10000 2T Built into the device Fuses 1000 VDC 15 A string Type II 40 kA 1000 VDC Type I II 5 kA 1000 VDC The AC elements required are as follows and must also be physically separated Model Circuit breaker Residual curre...

Page 13: ...13 QUICK GUIDE EQUINOX SOLAR INVERTERS Example of a junction box with DC protections on the left and AC protections on the right ...

Page 14: ...pply the device will not enter generation mode AC DC 4 The device will start up The LCD screen will turn on The following section details the steps to follow and explains how the console works Follow the steps below in order to stop the inverter and switch it off 1 Shut off the mains power supply Without a mains supply the device will stop generating 2 Shut off the solar park power supply Activate...

Page 15: ...ttings menu the language selection and the country of installation 5 2 PARAMETERS MENU Your new EQUINOX solar inverter comes pre configured to comply with the current Spanish regulations Therefore you only have to configure the parameters for the date time and price per kWh in order to obtain an approximate estimate of the savings to be made Press the ENT button to access the main menu Press the D...

Page 16: ... 00 x1 Cur EUR Va l 0 1 00 x2 Cur EUR Va l 0 1 20 x2 Setup Cash Setup Cash Setup Cash Setup Cash Setup Cash Setup Cash Setting the date and time Go back to the Settings menu If you are already on a menu page use the ESC button to exit Then use the DOWN ARROW to scroll through the menus until you reach the DATE TIME sub menu Press the ENT button to access it Press the ENT button to start setting th...

Page 17: ... 09 Date Time Time 16 45 00 x1 Fecha 09 03 2025 Fecha Hora Hora 16 45 00 x15 Changing the MPPT model By default the device is configured to connect 2 MPPTs To change the configuration to 1 MPPT go to the SET MODEL menu within the Settings menu Press the ENT button to access it Press the DOWN ARROW to select the 1 MPPT option Press the ENT button to confirm the selection Address Setup Menu Cash Pri...

Page 18: ...and DOWN ARROWS to enter the number of your choice Press ENT again to confirm the number and the line will then move on to the next number on the right The example below shows how to enter the password 2012 0 0 0 0 In pu t p ass wo rd 0 0 0 0 2 0 0 0 x1 2 0 0 0 x1 2 0 0 0 x1 2 0 1 0 x2 2 0 1 0 x1 2 0 1 2 In pu t p ass wo rd In pu t p ass wo rd In pu t p ass wo rd In pu t p ass wo rd In pu t p ass ...

Page 19: ...ch Duch Country Spain Germany UK Aus_default Belgium Denmark Holland Thailand Singapore Italy New Zealand Aus_Standard Power Settings Export P Set Lim Inv P Power Factor Gr Ti Mode Factor Set Model 2 MPPT 1 MPPT ISO Check ISO Level AntiReflux 10min 0V Run Param Aus Standard System Info Part No Serail No System Ver Cert Area Run Param U V Value 1 U V Time 1 O V Value 1 O V Time 1 Min F v 1 Min F T ...

Page 20: ...ency Possible fan malfunction Fault The inverter interrupts generation and goes into sleep mode due to anomalies in the mains or power supply Insufficient DC input voltage Mains undervoltage or overvoltage Mains under frequency or over frequency Fault The inverter interrupts generation and goes into sleep mode due to a severe anomaly The inverter s internal temperature is too high Overvoltage in t...

Page 21: ...us voltage high E004 Boost Fail Voltage step up malfunction E005 Grid OC Internal AC overcurrent E006 OTP The inverter s internal temperature is too high E007 Lo Iso R Isolation impedance low E008 IGBT drv IGBT protection activated E009 Int Comm Internal slave master communication error E010 Ileak Fail Leakage current high E011 Relay Fault Inverter output relay malfunction E012 Fan Fail Inverter i...

Page 22: ...G AND INSTALLING THE APP ON YOUR SMARTPHONE Download the EQX sun app from either the Play Store Android or App Store iOS depending on your smartphone s operating system After you have downloaded the app follow the instructions it will give you ...

Page 23: ...23 QUICK GUIDE EQUINOX SOLAR INVERTERS ...

Page 24: ...la Serra 100 08460 Palautordera BARCELONA Tel 34 93 848 24 00 sst salicru com SALICRU COM www linkedin com company salicru salicru_SA Product Range Uninterruptible Power Supplies UPS Stabilisers Step Down Light Dimmers Power Supplies Static Inverters Photovoltaic Inverters Voltage Stabilisers Variable Frequency Drives REF EN106E01 REV E CODE 401 ...

Reviews: