Version B June, 2020
20
MagnaRam-SK
4.3 Install Air Supply Hose.
1. Close all ball valves on the upper frame:
a. P1- Main air supply Primary
b. P2- Control air supply
c. P3 - Pump #1 air supply.
d. P4 - Pump #2 air supply.
e. P5 – Depressurization valve (Option).
f. H1 – High Pressure Material Pump 1.
g. H2 – High Pressure Material Pump 2.
2. Install air supply hose to the P1 Main air connection 1in. NPT.
a. Depending on the pump package selected the air requirement can range from 200-480cfm at
87 psi (6bar). Select the size and length of the air supply hose accordingly.
3. Open P1 and P2 Ball valves and check for leaks.
a. Run the elevator up and down.
i. Verify that there are no clearance issues.
ii. Verify the hose routings, it should not kink or stretch when the elevator is moved.
Plant Air
Supply
P1 Main Air
Connection
Air Hose
Magnaram show raised with
drum in place.
Main Air
Supply
Connection
P1
Controller
ball valve
P2
Main and Controller
Lockouts
Summary of Contents for Magna-Ram
Page 1: ...USER MANUAL Magna Ram 300 Gallon Elevator and Controls...
Page 17: ...Version B June 2020 17 MagnaRam SK 3 2 Ram Retracted 3 3 Ram Extended...
Page 18: ...Version B June 2020 18 MagnaRam SK 3 4 Load Height...
Page 43: ...Version B June 2020 43 MagnaRam SK 7 6 4 Control Box Door Layout...
Page 44: ...Version B June 2020 44 MagnaRam SK 7 6 5 Control Box Subplate Layout...
Page 45: ...Version B June 2020 45 MagnaRam SK 7 6 6 Control Box Back Layout...
Page 80: ...Version B June 2020 80 MagnaRam SK 10 Control Drawings 45 0538 00 Drawings...