6-2
EB 8061 EN
Start-up
Before start-up or putting the valve back into
service, make sure the following conditions
are met:
− The valve is properly installed into the
pipeline (see the 'Installation' section).
− The leak and function tests have been
completed successfully (see the 'Testing
the installed valve' section).
− The prevailing conditions in the plant
section concerned meet the valve sizing
requirements (see information under 'In-
tended use' in the 'Safety instructions
and measures' section).
Start-up/putting the valve back into opera
-
tion
1. Allow the valve to cool down or warm up
to reach ambient temperature before
start-up when the ambient temperature
and process medium temperature differ
greatly or the medium properties require
such a measure.
2. Slowly open the shut-off valves in the
pipeline. Slowly opening these valves
prevents a sudden surge in pressure and
high flow velocities which can damage
the valve.
3. Check the valve to ensure it functions
properly.
Summary of Contents for EB 8061 EN
Page 28: ...3 14 EB 8061 EN...
Page 34: ...4 6 EB 8061 EN...
Page 80: ...12 2 EB 8061 EN...
Page 82: ...13 2 EB 8061 EN...
Page 84: ...14 2 EB 8061 EN...
Page 85: ...EB 8061 EN 14 3...
Page 86: ...14 4 EB 8061 EN...
Page 91: ......